Primary Processing Plant for Fruits and Vegetables Flashcards
product handling which include steps to make a harvested commodity more suitable for manufacturers or consumers
Primary Processing
process of classifying into groups according to a set of recognized criteria of quality and size, each group bearing an accepted name and size grouping
Grading
process of classifying into sizes according to criteria that may or may not be recognized or accepted by the industry
Sizing
Process of classifying into groups designated by the person classifying the produce either according to a set of criteria or whatever criteria he may set
Sorting
ratio of the volume of air that enters a room to the volume of air of the empty room
Air change ratio
process of determining whether the grade standards have been interpreted or enforced properly by inspecting random samples usually of predetermined amount large enough to give an indication of the correctness of the grading procedure
Inspection
process to ensure adequate protection and safe delivery of a product from the producer to the ultimate consumer
Packaging
Capacity of the processing plant shall be calculated based on the volume of commodity being processed. An area of ___ square meter per ton of commodity shall be provided.
Capacity of the processing plant shall be calculated based on the volume of
commodity being processed. An area of 20 square meter per ton of commodity shall be provided.
The storage area of a processing plant shall have a capacity for temporary storage of raw materials for __ - __ processing days.
The storage area of a processing plant shall have a capacity for temporary storage of raw materials for 2-5 processing days.
Ceilings shall be at least ___ m from the finished floor line.
Ceilings shall be at least 2.4 m from the finished floor line.
All wall tops and ledges shall slope at __ degrees.
All wall tops and ledges shall slope at 45 degrees.
It shall be coved to the floor-wall and at wall-to-wall junctions with a minimum radius of __mm -__mm.
It shall be coved to the floor-wall and at wall-to-wall junctions with a minimum radius of 50 mm - 60 mm.
All windows shall be properly installed with __-mesh screen.
All windows shall be properly installed with 16-mesh screen.
Window ledges shall be sloped about __ degrees to prevent the accumulation of dirt, water, or debris
Window ledges shall be sloped about 45 degrees to prevent the accumulation of dirt, water, or debris
Windowsill shall be at least __m from the finish floor line.
Windowsill shall be at least 1 m from the finish floor line.