Practice Exam 2 Flashcards

1
Q

What is a best practice for managing contractor RFIs?

A

Using project management software to create, track, and manage RFIs effectively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is maintaining an RFI log considered a best practice?

A

It helps track the order of review, date received, and due dates, ensuring timely responses and efficient management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do standard file naming conventions support RFI management?

A

They make files easier to find, less confusing, and more searchable, improving overall project efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the architect’s responsibility regarding the contractor’s submittal schedule per B101, Article 3.6.4.1?

A

The architect must review and approve the contractor’s submittal schedule to appropriately staff the project during the construction phase. This should not be confused with the project schedule, which is the contractor’s sole responsibility and not subject to the architect’s review or approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When does the architect conduct inspections of the work according to AIA B101?

A

The architect conducts inspections only at substantial completion and final completion per B101, Article 3.6.6.1. While the architect visits the site to observe work at intervals appropriate to the stage of construction (Article 3.6.2.1), these visits are not considered inspections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which design criteria are typically established by zoning regulations?

A

Building setbacks,
Signage requirements,
Parking requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which criteria are not established by zoning regulations but are determined by the building code?

A

Construction type
Occupancy, classification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a firm’s commissioning checklist, and what is its purpose?

A

A firm’s commissioning checklist is a tool used to ensure that building systems are designed, installed, and functioning as intended. It includes steps for verifying that the project meets the owner’s requirements, complies with design specifications, and operates efficiently. This checklist is typically used by the commissioning authority during pre-design, design, construction, and post-occupancy phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which performance and design criteria should be included for commissioning and exterior wall design?

A

Joints at system interfaces: Critical to prevent building performance failures by ensuring proper detailing and material compatibility.

Structural support: Essential for stability and avoiding settling that could compromise the wall system’s integrity.

Material/finish durability: Ensures the building performs as intended, with finishes lasting appropriately.

Barrier issues: Proper use of air, vapor, and other barriers is crucial for expected building envelope performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What information is typically requested as part of an RFQ (Request for Qualifications) submittal?

A

Similar project experience: Demonstrates the architect’s expertise for the new project.

Previous client references: Allows the client to vet the architect and ensure compatibility.

Letter of interest: Shows the firm’s enthusiasm, understanding of the project, and motivations beyond financial gain.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a typical architectural fee percentage for the bidding and negotiations phase?

A

Five percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the typical architectural fee percentage for the construction documents and bidding/negotiations phase of a BIM project?

A

25%. This is because BIM projects spend more time in the earlier phases creating the model, leading to less time spent on documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In a typical design-bid-build project, what percentage of the total fee is accounted for by the construction documents and bidding phases combined?

A

About 45%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which AIA forms are appropriate for an architect hired as the design architect for an existing project team that has an architect of record and an interior designer?

A

B101: Agreement between the architect and owner. It outlines services, scope, payment, and responsibilities between the architect and the owner.

C101: Agreement between architects. Used when there are multiple architects on a project, explaining scope, collaboration, and payment terms.

C401: Agreement between an architect and a consultant. This form is used when the architect hires consultants directly, outlining scope and payment terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you calculate the architect’s labor percentage from the total fee when given the following variables?

Client’s budget: $3,500,000
Architect’s fee percentage: 8%
Consultant’s fee percentage: 25%
Architect’s profit percentage: 15%

A

Calculate the total architect’s fee:
Multiply the client’s budget by the architect’s fee percentage.
$3,500,000 x 8% = $280,000

Subtract the consultant’s fee:
Multiply the total fee by 75% (since 100% – 25% = 75%).
$280,000 x 75% = $210,000 (the fee remaining after consultants are paid).

Calculate the architect’s profit:
Multiply the architect’s total fee by the profit percentage.
$280,000 x 15% = $42,000 profit.

Subtract the profit from the remaining fee:
$210,000 – $42,000 = $168,000 (the amount left for labor).

Calculate the labor percentage:
Divide the labor amount by the total architect’s fee.
$168,000 / $280,000 = 60%

Conclusion:
60% of the total architect’s fee is allocated for labor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

An AIA member has been found guilty by the National Ethics Council of not giving appropriate professional credit to their former firm when publishing completed projects on their personal website. Which of the following penalties can the National Ethics Council impose?

A

Nonpublic admonishment
The National Ethics Council can issue a nonpublic admonishment, which is a common punishment for relatively minor infractions. This involves privately warning and reprimanding the AIA member about their actions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When would the suspension of a license apply to an architect?

A

Suspension or revocation of a license is determined by individual jurisdictions, not the AIA. It typically applies when the architect has committed serious ethical violations, such as criminal activity, gross negligence, or unethical conduct that directly endangers public safety or violates licensing laws.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When might a monetary fine be imposed on an architect?

A

Monetary fines may be imposed by governmental bodies or legal jurisdictions, not the AIA. These fines are typically applied when an architect violates local laws or regulations, such as failing to pay taxes, violating building codes, or engaging in criminal activity. The AIA, as a trade organization, does not have the authority to impose monetary fines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When might civil penalties be imposed on an architect?

A

Civil penalties are imposed by the legal system, not the AIA. These penalties may apply when an architect violates laws or regulations that result in harm to others, such as negligence, fraud, or breach of contract. The affected party must file a lawsuit in the appropriate legal jurisdiction to seek civil penalties, which may include financial compensation for damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the steps in the Evidence-Based Design process?

A

Question,
Collect data,
Hypothesize,
Design,
Construct,
Analyze,
Refine question,
Share results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What factors should be considered when selecting technologies for design and documentation? Check the three that apply.

A

Knowledge management
Technologies for knowledge management help architects manage collective wisdom by integrating data collection and documentation into existing management practices.

Project schedule
Technologies like BIM help shorten project durations, tighten production control, and improve schedule conformance.

Project delivery method
The project delivery method influences how technologies are applied. Different methods (e.g., design-bid-build, design-build, etc.) require different approaches to coordination, communication, and documentation, impacting the choice of technology.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the role of building codes in selecting technologies for design and documentation?

A

Building codes impact the design of a project, but they do not directly influence the choice of technologies and software an architect uses for design and documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How does the project site influence the selection of technologies for design and documentation?

A

The project site and jurisdiction affect the design of the building, but they do not impact the choice of technologies used for design and documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How does firm size affect the selection of technologies for design and documentation?

A

Firm size does not dictate the choice of technologies and software an architect uses for design and documentation. The selection is based on other factors, such as project needs and objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is a project team member check-in, and how does it relate to quality control in a firm’s process?

A

A project team member check-in is a method described in the firm’s process to ensure that team members are on task to meet deadlines and that the project is on track. Internal communication is essential for managing quality control and project progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

How do task checklists contribute to quality control in a firm’s process?

A

Task checklists are a crucial part of project management and quality control. They help ensure that team members are clear about their roles and allow the project manager to track the progress of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is an internal quality control review, and how does it fit into the firm’s process?

A

An internal quality control review is conducted by the project manager, who is part of the project team. It ensures the work is meeting the firm’s quality standards and is an essential part of the firm’s process for managing quality control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are working redline sets, and how do they contribute to quality control in the firm’s process?

A

Working redline sets are a part of the firm’s quality control process, where the project manager reviews and marks up the current set of drawings to ensure accuracy and compliance with project standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

How does a peer review differ from the quality control review conducted by the project manager?

A

A peer review is a review conducted by another professional at the same level but outside of the project team, whereas the project manager’s quality control review is internal and involves checking the work within the team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Why is extensive experience working on projects similar to the proposed project important when responding to an RFP?

A

Experience with projects of the same type as the proposed project (e.g., multi-family, hospitality) demonstrates the firm’s relevant expertise, making it a strong qualification for the prospective client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Why is having more than half of a firm’s clients as repeat customers a valuable qualification to highlight in an RFP?

A

Repeat clients indicate that the firm consistently delivers quality work, understands client needs, and builds long-term relationships, all of which are valuable to the prospective client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

How does a firm’s experience with the USGBC LEED certification program relate to relevant qualifications for an RFP?

A

While experience with LEED certification is valuable, it may not always be directly relevant to every project. It is not universally applicable to all project types and thus might not be the best example to highlight in this case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Why would the principal architect’s graduation from the same university as the client not be relevant for an RFP?

A

Shared educational backgrounds, such as attending the same university, do not demonstrate the architect’s relevant experience or skills in architectural services and are not significant qualifications for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Why is designing many buildings in the same market as the client’s company an important qualification to highlight in an RFP?

A

Experience in the same market sector (e.g., educational, industrial, or civic buildings) shows that the firm is familiar with the specific needs and challenges of that market, making it a relevant qualification for the prospective client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Why is experience working in the same town as the proposed project valuable in an RFP?

A

Familiarity with local city codes, ordinances, and regulations enhances the firm’s ability to navigate local requirements, which makes the firm well-suited for the proposed project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Why should the exterior wall specifications be finalized at the end of the CD phase?

A

At the end of the CD phase, all exterior wall specifications should be complete to ensure accuracy and clarity in the construction documents before the project moves forward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Why is it important to confirm that the owner’s project requirements (OPR) are included in the exterior wall commissioning checklist?

A

Confirming that the OPR are included ensures that the project meets the owner’s expectations and requirements. It’s crucial for aligning the design with the client’s needs before the final construction documents are issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Why are means and methods drawings not included in the exterior wall commissioning checklist?

A

The architect is not responsible for means and methods, which are typically provided by the contractor. Including them in the architectural drawing set could expose the architect to undesired liability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Why must exterior elevations be graphically complete at the end of the CD phase?

A

At the end of the CD phase, all exterior elevations should be complete and clearly labeled to ensure that all exterior walls are accurately depicted and easily referenced in the drawing set.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Why should foundation sections be completed at the end of the CD phase?

A

Foundation sections are critical to the building envelope. Incomplete foundation details can lead to issues like water intrusion or poor thermal performance, so they must be finalized at the end of the CD phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Why is it incorrect to note exterior wall performance criteria on the drawings rather than in the specifications?

A

Exterior wall performance criteria should be documented in the specifications to provide detailed information about performance standards, while the drawings focus on visual and construction details.

42
Q

What factor determines whether a worker is classified as a full-time employee or an independent contractor based on financial control?

A

If the worker controls the business aspects of their job, such as paying for their own expenses and having the opportunity for both financial gains and losses, they are more likely to be classified as an independent contractor. Employees are typically paid a fixed salary and do not bear such financial risks.

43
Q

How does the type of relationship influence whether a worker is an employee or an independent contractor?

A

If a worker receives employee benefits such as insurance, pensions, or paid time off, they are more likely to be classified as an employee. If the worker does not receive these benefits, they may be classified as an independent contractor.

44
Q

Why is the number of hours worked not a determining factor in whether a worker is an employee or an independent contractor?

A

The number of hours worked does not determine employment status. Both employees and independent contractors can work varying hours, so the nature of the relationship is more important than the number of hours worked.

45
Q

How does the degree of behavioral control affect whether a worker is classified as an employee or an independent contractor?

A

If the employer has the right to control what and how the worker performs their tasks, the worker is more likely to be classified as an employee. If the employer does not control the methods used by the worker, they are more likely to be classified as an independent contractor.

46
Q

Why is the location where work is performed not a determining factor in whether a worker is an employee or an independent contractor?

A

The location where work is performed (e.g., home office or company office) does not affect the classification. Employment status is based on other factors such as control over the work and the type of relationship between the worker and employer.

47
Q

How does spending more time on non-billable tasks affect the firm’s profitability?

A

Profit

Spending more time on non-billable tasks leads to fewer billable hours, which decreases gross revenue, potentially lowering profit.

48
Q

Which metric is impacted by the number of billable hours an architect works, and the amount of non-billable tasks they perform?

A

Gross revenue

Gross revenue is directly affected by the number of billable hours. More non-billable tasks result in reduced billable hours and lower revenue.

49
Q

Which financial metric remains unaffected by the amount of time an architect spends on non-billable tasks?

A

Workers’ compensation premiums

Workers’ compensation premiums are based on employee classification and payroll, not the amount of time spent on billable or non-billable tasks.

50
Q

Why does spending more time on non-billable tasks not affect the net multiplier?

A

Net multiplier

The net multiplier is determined by an annual profit plan, so a single week’s change in billable time has negligible impact on it for the current or future years.

51
Q

Which financial metric reflects how an architect’s non-billable work time affects the overall revenue generated by the firm?

A

Expenses

The architect’s non-billable hours do not directly affect the firm’s expenses, as this metric is related to operational costs and not individual productivity.

52
Q

Question: What qualification of a construction manager can impact the success of a project?

A

Constructability expertise.
Explanation: The construction manager’s knowledge of the realities of actually building the design can significantly impact changes and conflicts during construction.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9.2

53
Q

What qualification of a construction manager can impact the success of

A

Team chemistry.
Explanation: Although not the most critical, good team relationships foster collaboration, which is key to a successful project.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9.2

54
Q

Does LEED certification impact the success of a construction manager on a project?

A

No.
Explanation: While LEED certification shows understanding of sustainable principles, it does not directly impact the construction manager’s ability to manage the success of the project.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9.2

55
Q

Does the office size of the construction manager impact their success on the project?

A

No.
Explanation: The office size may influence capacity but does not impact the actual success of the project, especially if the firm has completed similar jobs.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9.2

56
Q

Does proximity to the job site affect a construction manager’s success?

A

No.
Explanation: Although proximity reduces fees, the location does not necessarily impact a construction manager’s success, as a better-suited manager may be found further away.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9.2

57
Q

What is the purpose of using mock-ups in a project?

A

Mock-ups
Explanation: Mock-ups are used to create a tangible model of the desired outcome before committing to the final construction, ensuring design intent is achievable.

Reference (back of card): The Architect’s Handbook of Professional Practice, 15th edition, pp. 304-305

58
Q

What is the role of a code plan review in quality assurance?

A

Code plan review
Explanation: A code plan review involves reviewing the drawing set to ensure compliance with local codes, ensuring that the project meets legal and quality standards.

Reference (back of card): The Architect’s Handbook of Professional Practice, 15th edition, pp. 304-305

59
Q

How do submittals contribute to quality assurance in a project?

A

Submittals
Explanation: Submittals are reviewed to verify that the subcontractor’s or fabricator’s work meets the design intent, ensuring quality in materials and construction methods.

Reference (back of card): The Architect’s Handbook of Professional Practice, 15th edition, pp. 304-305

60
Q

What is the benefit of conducting a peer review in the design process?

A

Peer review
Explanation: Peer review is when another team member or architect reviews the drawing set, helping to catch potential errors and ensure quality control.

Reference (back of card): The Architect’s Handbook of Professional Practice, 15th edition, pp. 304-305

61
Q

Does printing final drawings in-house contribute to quality assurance?

A

Printing final drawings in-house
Explanation: Printing drawings in-house does not directly contribute to ensuring quality in the design or construction process, so it is not considered a QA process.

Reference (back of card): The Architect’s Handbook of Professional Practice, 15th edition, pp. 304-305

62
Q

How are addenda used in a project?

A

Addenda
Explanation: Addenda are used to provide information or clarify project details but are not considered part of the quality assurance process.

Reference (back of card): The Architect’s Handbook of Professional Practice, 15th edition, pp. 304-305

63
Q

Which log helps track phone communications during construction administration?

A

Answer: Phone log

Explanation: A phone log is used to track the progress of the project and serves as a tool for recording and verifying communication between team members during the construction phase.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 594-595

64
Q

Question: What is the purpose of a submittal log in construction administration?

A

Answer: Submittal log

Explanation: A submittal log is used to track the progress of submittals during construction, ensuring that all required materials and documents are reviewed and approved in a timely manner.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 594-595

65
Q

What is the most likely result if a consultant’s professional liability insurance is inadequate and damages need to be paid?

A

Answer: The liability transfers to the architect and their insurer.

Explanation: In situations where a consultant’s insurance is inadequate, many legal cases have found the architect ultimately responsible for the work. This can extend to the situation where the consultant’s negligence results in damages, as the architect is contracted for the overall project. Even if there is an indemnification clause in the consultant’s agreement, it may not fully protect the architect if the consultant’s insurance is insufficient.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, p. 174

66
Q

Question: Which of the following items is not typically included in an employee handbook?

A

Answer: Costs of benefits package

Explanation: Employee handbooks typically include general information about available benefits but do not include detailed costs for benefits packages. Such information is usually distributed separately, often during annual enrollment periods, and may be subject to changes on a yearly basis.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 452-456

67
Q

What items are typically included in an employee handbook? Check the three that apply.

Acknowledgement and receipt of handbook?

Human resources contact information?

Costs of benefits package?

Standards on workplace violence prevention?

A

Answer:

Acknowledgement and receipt of handbook

Human resources contact information

Standards on workplace violence prevention

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 452-456

68
Q

Why can energy consumption be studied using BIM technology?

A

Energy consumption: BIM technology can create energy models that simulate and analyze energy consumption, helping to improve building performance over its lifecycle.

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 1026-1028

69
Q

Why can life cycle analysis be studied using BIM technology?

A

Life cycle analysis: BIM technology enables the simulation of a building’s lifecycle, including long-term costs, maintenance, and energy consumption, facilitating better decision-making.

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 1026-1028

70
Q

Why can project cost be studied using BIM technology?

A

Project cost: BIM assists in cost estimation by providing real-time data on materials, labor, and other resources, improving accuracy in budgeting and managing costs.

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 1026-1028

71
Q

Why is project billing not something that can be studied with BIM technology?

A

Project billings: BIM does not handle accounting tasks like project billings. These are typically managed with specialized accounting software.

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 1026-1028

72
Q

Why is consultant coordination not typically managed through BIM technology?

A

Consultant coordination: Although BIM improves coordination in terms of coordinated drawings, managing consultant coordination is handled outside BIM by the architect.

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 1026-1028

73
Q

Why is project schedule not studied using BIM technology?

A

Project schedule: BIM does not study the project schedule itself, though it can help optimize the design and identify potential schedule issues. Project scheduling is typically managed through separate scheduling software.

Reference:
The Architect’s Handbook of Professional Practice, 15th Edition, pp. 1026-1028

74
Q

Why is the owner responsible for furnishing civil surveys in an AIA Owner-Architect agreement?

A

The owner is responsible for furnishing civil surveys because they are required to provide surveys that describe the legal and physical characteristics of the project site, which are essential for the architect to develop the design.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 409-410

75
Q

Why is the owner responsible for providing information and approvals in a timely manner in an AIA Owner-Architect agreement?

A

The owner is responsible for providing information and approvals in a timely manner because delays in providing essential information can impact the project’s schedule and progress, and can cause delays to the design and construction phases.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 409-410

76
Q

Why is the architect responsible for coordinating design-team consultants in an AIA Owner-Architect agreement?

A

The architect is responsible for coordinating the work of design-team consultants under the C401 agreement, ensuring that their work aligns with the project’s design and objectives.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 409-410

77
Q

Why is the owner not required to contract with the architect to hire environmental consultants in an AIA Owner-Architect agreement?

A

The owner is not required to contract with the architect to hire environmental consultants because it is the owner’s responsibility to directly contract these services, as they are outside the scope of the architect’s responsibilities.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 409-410

78
Q

Why is the owner responsible for providing and updating the project budget in an AIA Owner-Architect agreement?

A

The owner is responsible for establishing and updating the project budget because they are in control of the financial resources for the project, and it is essential for the architect to have an accurate budget for proper project planning and design.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 409-410

79
Q

Why is the owner responsible for furnishing a geotechnical report in an AIA Owner-Architect agreement?

A

The owner is responsible for furnishing the geotechnical report as it provides necessary information on the soil conditions and environmental factors that impact the design and construction of the facility.

Reference: The Architect’s Handbook of Professional Practice, 15th Edition, pp. 409-410

80
Q

Why can an architect sign and seal documents not prepared under their direct supervision in certain cases according to NCARB’s rules of conduct?

A

An architect can sign and seal documents not prepared under their direct supervision in two cases: (1) when reviewing standard manufacturer’s details or installer’s details, and (2) when reviewing prototypical building documents prepared by another architect from any jurisdiction, ensuring they conform with local codes.

Reference: NCARB Model Rules of Conduct, rule 5

81
Q

Why can an architect sign and seal standard manufacturer’s details or installer’s details not prepared under their supervision according to NCARB’s rules of conduct?

A

An architect can sign and seal these details if they have reviewed them, as these documents are generally standard and have been evaluated for their conformity with the project’s design requirements.

Reference: NCARB Model Rules of Conduct, rule 5

82
Q

Why can an architect sign and seal prototypical building documents not prepared under their supervision according to NCARB’s rules of conduct?

A

An architect can sign and seal prototypical building documents if they have reviewed the documents to ensure they conform with local codes, even if the documents were prepared by another architect from a different jurisdiction.

Reference: NCARB Model Rules of Conduct, rule 5

83
Q

Why can Employee A sign and seal the residential remodel documents prepared by a junior employee?

A

Employee A can sign and seal the residential remodel documents because they were prepared under their direct supervision, which is a situation where an architect can legally sign and seal documents according to NCARB’s rules of conduct.

Reference: NCARB Model Rules of Conduct, rule 5

84
Q

Why is reviewing and comparing bids a role of the architect when helping a client select a contractor?

A

The architect reviews and compares the bids to identify any anomalies, verify adherence to the bidding instructions, and ensure the bids align with the contract documents. The architect typically compiles a spreadsheet for easier comparison.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

85
Q

Why is asking thoughtful questions during contractor interviews a role of the architect when helping the client select a contractor?

A

The architect is involved in the interview process to ask relevant questions about the bids, clarifying details and ensuring the client has the necessary information to make an informed decision.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

86
Q

Why is commenting on personal or firm experience with a contractor a role of the architect when helping a client select a contractor?

A

The architect can assist by providing unbiased feedback about the contractor’s past work, ensuring that their comments remain professional and focused on the contractor’s ability to perform as expected.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

87
Q

Why is reviewing references from a contractor’s completed projects a role of the architect when helping the client select a contractor?

A

The architect can follow up on references, review the contractor’s previous work, and provide insight into the contractor’s performance and reliability, helping the client make a more informed selection.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

88
Q

What is the formula for calculating the project labor budget?

A

The project labor budget is calculated using the formula:

Project Labor Budget = Net Service Revenue - Direct Expense Budget - Contingency Budget

This formula ensures that the labor costs are appropriately accounted for by subtracting other necessary expenses from the total revenue.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9

89
Q

What is the typical percentage range for contingency amount based on an architect’s fee?

A

Contingency amounts are generally calculated as 2% to 10% of the architect’s fee, depending on the type of contingency. In this case, the contingency is 3%, which is within the typical range.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9

90
Q

What is included in the calculation of net service revenue (NSR)?
Answer:

A

NSR is calculated by subtracting consultant fees from the gross fee. If consultant fees are overbudgeted, it will result in a lower NSR than expected.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9

91
Q

What is the typical range for an architect’s fee based on the construction budget?

A

The architect’s fee is typically based on 7% of the estimated construction budget, which is within the standard range for architectural fees.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9

92
Q

What is the typical percentage of the budget allocated for consultant fees in architectural projects?

A

Typically, consultant fees are lower than 40% of the total budget, depending on the size of the project and the number of consultants involved. In this case, the architect has overbudgeted consultant fees at 40%.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 9

93
Q

Which consultant is required due to the extent of plumbing for the new coffee bar?

A

Plumbing consultant
A plumbing consultant is required for the design due to the complexity and extent of the plumbing needs for the coffee bar.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

94
Q

Which consultant is required for the design of a new skylight structure and a stair structure?

A

Structural engineer
A structural engineer will be required to design the new skylight structure and stair structure.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

95
Q

What is the fee for additional services if the construction cost of the scope revisions is $28,500 and the architect’s fee is based on 7% of the construction cost?

A

$2,850
The fee for additional services will be calculated at 10% of the construction cost of the scope revisions. Since the construction cost is $28,500, 10% of this amount equals $2,850.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

96
Q

How do you solve for the architect’s percentage fee when given the gross project fee and architect’s fee?

A

Formula:
Architect’sPercentageFee = (Architect’sFee / GrossProjectFee) × 100

Example:
140,000 / 2,000,000 × 100 = 7%

Explanation:
The architect’s percentage fee is calculated by dividing the architect’s fee by the gross project fee and multiplying by 100 to express it as a percentage.

Reference: The Architect’s Handbook of Professional Practice, 15th edition, Chapter 10

97
Q

How many hours per week can Employee 4 devote to the project to stay on track for achieving the firm’s financial goals during the construction administration (CA) phase?

A

Formula:

  1. Calculate the percentage of the architect’s fee allocated to the architectural staff for CA:

Architect’s fee for CA = Total CA Fee × (100% - Consultant Allocation Percentage)

  1. Calculate the weekly fee:
    Weekly Fee = Architect’s Fee for CA / Number of Weeks for CA
  2. Calculate the hours per week
    Employee 4 can work:
    Hours per Week = Weekly Fee / Employee’s Hourly Rate

Steps:

Find the percentage of the fee allocated to the architect’s staff for CA:
$60,200 / $215,000 = 28%
100% - 28% = 72%

Find the fee allocated to the architect’s staff for CA:
72% × $38,700 = $27,864

Find the weekly fee:
$27,864 / 11 weeks = $2,533.09 per week

Find the hours per week Employee 4 can work:
$2,533.09 / $110 per hour = 23 hours (rounded)

Explanation:
The calculation ensures that Employee 4 can work a reasonable number of hours per week based on the allocated CA fee and their hourly rate. The rounding accounts for work being distributed evenly across the project duration.

Reference: Firm Staffing Document and Project Budget

98
Q

Which team member is the best choice to manage the project?

A

Employee 6 is the best choice to manage the project because they have experience in office and restaurant design, which will be beneficial for the office and break room components of the project. Additionally, Employee 6 is the only project manager with experience working with the owner, which is crucial for effective client communication and project management.

Explanation:
The project manager needs to have both relevant design experience and familiarity with the owner, as managing client relationships and understanding project requirements are key to successful project execution.

Reference: Firm Project Team Selection Guidelines

99
Q

How do you calculate the percentage of time being spent on the project by Team 1?

A

To calculate the percentage of time Team 1 will spend on the project, follow these steps:

Determine total hours: The total project labor budget is 600 hours.

Determine Team 2’s hours: Team 2 works at the planned pace of 37.5 hours per week for 13 weeks:
37.5 hours/week × 13 weeks = 487.5 hours.
38.
Calculate Team 1’s hours: Subtract Team 2’s hours from the total project hours:
600 hours - 487.5 hours = 112.5 hours for Team 1.

Calculate Team 1’s percentage of total project hours:
112.5 hours ÷ 600 total hours = 18.75%, which rounds to 19%.

Explanation:
The percentage reflects the proportion of total project hours allocated to Team 1 after accounting for Team 2’s extended schedule.

Reference: Project Labor Budget Guidelines

100
Q

How do you calculate the fixed fee for the workplace portion of the project based on past project history?

A

To calculate the fixed fee for the workplace portion of the project, follow these steps:

Determine the historical cost per square foot:

1 year ago (Project 5): $79,200 ÷ 6,000 sf = $13.20 per sf
2 years ago (Project 1): $75,000 ÷ 6,250 sf = $12.00 per sf
Calculate the percentage increase:

$13.20 ÷ $12.00 = 1.1, which indicates a 10% increase in fees.
Determine the new cost per square foot:

$13.20 per sf × 1.1 = $14.52 per sf.
Calculate the total fixed fee for the workplace portion of the project:

Total area: 6,805 sf
$14.52 per sf × 6,805 sf = $98,808.60, rounded to $98,809.

Explanation:
The fixed fee is determined by applying the percentage increase in cost per square foot to the historical data, and then multiplying by the current total area of the workplace portion.

Reference: Project Fee Calculation Methods