4.2: Evaluate Design, Coordination, and Documentation Methodologies for the Practice Flashcards

1
Q

Building information modeling (BIM)

A

A type of architectural documentation which affixes parameters and other data to typical elements of the drawing set, such as doors, walls, and windows.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project manual

A

The project manual consists of the written documents created for the purposes of procuring and constructing the work, which can include things such as the instructions to bidders, bid requirements, specifications, etc. The contract drawings, which include things such as plans, sections, elevations, and details, are separate from the project manual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

RFI

A

RFI stands for request for information. This is a form of documented correspondence between members of the project team and may be submitted to the owner, architect, or contractor. Issues that arise during construction that require clarification should be addressed through the RFI process so that an official log can be referenced later if needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Special conditions

A

Special conditions are used to further extend the supplementary conditions of the contract for construction. Government clients often have special conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Specifications

A

A type of technical standards documentation which outlines the types of materials, products, and procedures to be utilized in constructing the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Work plan

A

A schedule describing the tasks and milestone dates a person or team must complete on a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly