Give the definition and a few examples of Enterprise Environmental Factors

A

Conditions, not under the immediate control of the team, that influence, constrain or direct the project, programme, or portfolio

Internal

  • Culture, structure, governance
  • Geographic distribution
  • Infrastructure
  • IT
  • Resource availability
  • Employee capability

External

  • Marketplace
  • Social and cultural influences
  • Legal
  • Commercial databases
  • Academic research
  • Government or industry standards
  • Financial e.g. exchange rates, interest rates
  • Physical environment, e.g. weather
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Give the definition and a few examples of the Organisational Process Assets

A

Plans, processes, policies, procedures and knowledge bases that are specific to and used by the performing organisation

Initiating; Planning

  • HR policies, procurement policies, etc
  • Project Management Methods, Process audits, checklists, etc
  • Templates, e.g. project mgmt plans, report formats, risk categories
  • Preapproved supplier lists

Executing, monitoring & controlling

  • Change control procedures
  • Traceability matrices
  • Financial control procedures
  • Issue and defect mgmt procedures
  • Organisational communication requirements

Closing

  • project evaluation
  • deliverable acceptance

Organisational knowledge repositories

  • Configuration (versions of software)
  • Financial data
  • Lessons learned
  • Project files
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a tight matrix?

A

The collocation of the project team (unrelated to matrix organisation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the project team?

And the project management team?

A

Project team: full team incl manager

Project mgmt team: project manager + people appointed to support the manager in the project mgmt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is alternative analysis?

How is this different from cost benefit analysis?

A

A technique used to evaluate identified options in order to select the options or approaches to use to execute the project.

  • using staff with lower skills levels instead of experts > consequences on time to complete, cost, risk
  • renting a larger truck > cost more, but fewer trips?

Cost benefit analysis mainly refers to the trade off of (quality) benefits of the deliverables of the project to the cost. So not “how shall we do this activity?” But “is this activity worth it in relation to the output of the project?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a performance review?

A

A technique that is used to measure, compare, and analyse actual performance of work in progress on the project against the baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is what-if scenario analysis and what is it used for?

A

The process of evaluating scenarios in order to predict their effect, positive or negative, on project objectives. It is a data analysis technique that can be used during e.g. develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is reserve analysis and what how is it used?

A

An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or fund for a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an affinity diagram?

A

A simple way of visually grouping ideas into themes for review and analysis. A data representation technique for process Collect Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a cause-and-effect diagram?

A

Aka fish bone diagram or why-why diagram, grouping causes together in branches. Is a data representation technique for process Manage Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a logical data model?

A

Visual representation of an organisation’s data, used to identify where data integrity or other quality issues arise. Used as a technique in plan quality management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a matrix diagram?

A

A way to visualise the strength of relationship between different factors, causes and objectives that exist between the rows and the columns that form the matrix.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a probability and impact matrix and what is it used for?

A

A grid for mapping the probability of each risk occurrence and its impact on project objectives if that risk occurs. It is used in the perform qualitative risk analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the project life cycle?

A

Performing organisation’s methodology for managing projects, e.g. plan-driven, change-driven etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a project life cycle phase?

A

Example: Analysis, Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a project expediter?

A

Xxx

17
Q

What is work performance data?

A

The raw observations and measurements identified during activities being performed to carry out project work

18
Q

What is work performance information?

A

The performance data collected from controlling processes, analyzed in comparison with project management plan components, project documents, and other work performance information

19
Q

What are work performance reports?

A

Representation of work performance information compiled in project documents, intenden to generate decisions, actions, or awareness

20
Q

What are the business documents?

A

Business case, benefits management plan

21
Q

What is organisational project management (OPM)?

A

A framework and direction for how projects, programmes and portfolios, and organisational work should be done to meet the organisations strategic goals

22
Q

Who should collect the lessons learnt?

A

All the stakeholders