Chapter 6 - Schedule Mgmt Flashcards
What is in the schedule mgmt plan?
-Scheduling methodology and software
-rules for how estimates should be stated e.g. hours or weeks
-scheduled baseline
-A threshold for acceptable variance
– performance measures that will be used on the project to identify variances early
– a plan for how schedule variances will be managed
– a process for determining whether a variance must be acted upon
– identification of schedule change control procedures
– Types of reports required on the project relating to schedule
– format and frequency of project reporting
– in an adaptive life-cycle: the length of releases and iterations
What is the precedence diagramming method?
A method to create a network diagram
What is a finish to start relationship?
Activity A must finish before activity B starts
What is a start to start activity?
Activity A must have started before activity B can begin
What is a finish to finish activity?
Activity A must have finished before activity B can finish
What is a start to finish activity?
Activity B must start before activity A can finish. Rarely used.
What is lead time?
Elite may be used to indicate that an activity can start before its predecessor activity is completed
What is lag time?
A like is waiting time inserted between activities, such as needing to wait three days after pouring concrete before constructing the frame for a house
What type of dependencies are there?
– Mandatory dependency (hard logic): e.g. due to nature of the work, or legal requirements
– discretionary dependency (preferred, preferential, or soft logic)
– external dependency
– internal dependency
What is path convergence?
When an activity has one or more activities directly preceding it
Note: this increases project risk
What is path divergence?
When an activity has one or more successors activities directly following it
What estimating methods are there
– one point estimating
– analogous estimating (top down)
– parametric estimating using e.g. regression analysis or learning curve
- heuristics, e.g. “design work is always 15% of project length”
– three point estimating using the triangular distribution or the beta distribution. Use straight/triangular when you have little historical information, beta/weighted when do have historical information
– bottom-up estimating
What are the inputs to Develop Schedule?
– Lessons learnt – project management plan (schedule management plan and scope baseline) – activity list and attributes – milestone list – assumption log – network diagram – basis of estimates –Activity duration estimates – resource requirement – resource calendars – resource breakdown structure – a company calendar identifying working and nonworking days – project team assignments – risk register
Which formula do you use to calculate float in forward pass?
The float equals late start minus early start
Which formula do you use to calculate float in backward pass?
Float equals late finish minus early finish