PM cards 9th 20 Flashcards
In the CPM, what is an early start?
The earliest date an activity can begin
In CPM, what is an early finish?
The earliest date an activity can finish.
How are early starts and early finishes determined in CPM?
By doing a forward pass on the diagram.
How are late finishes and late starts determined in CPM?
By doing a backward pass of the diagram.
Float time is also known as?
Slack time.
What is float time?
The amount of time the early start of a task may be delayed without delaying the finish date of the project.
What is duration compression?
The use of techniques such as fast-tracking or crashing to shorten the planned duration of a project or to resolve schedule slippage.
What is crashing?
This is a schedule compression technique that adds resources to the project to reduce the time it takes to complete the project.
What is fast tracking?
Performing two tasks in parallel that were previously scheduled to start sequentially.
What is the purpose of the project schedule?
to determine the start and finish dates for each of the project activities.
What are common ways to display the project schedule?
Network Diagrams, Milestone Charts, Gantt Charts
What is the schedule baseline?
The final, approved version of the project schedule that includes the baseline start and finish dates and resource assignments.
Once the scope statement and the WBS are developed, your next step in the planning phase is ____________.
Determining the resource requirements for the project.
What is Communications Planning?
the process of identifying what people or groups need to receive information regarding your project, what information each group needs, and how the information will be distributed.
During what stage does communications planning occur?
Planning Process Group