PM cards 10th 20 Flashcards

1
Q

The roles and responsibilities document is part of what plan?

A

The resource planning phase of the planning group process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a project organization chart?

A

it provide a snapshot of who is working on the project, but it also shows the reporting structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the staffing management plan?

A

Documents when and how human resources will be added to and released from the project team and what they will be working on while they are part of the team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What occurs during the staff acquisition process?

A

you’ll choose the team members (or organizations) who will work on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is procurement planning?

A

the process of identifying the goods and services required for your project that will be purchased from outside the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The ____________ details the goods or services you want to procure.

A

Statement of Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the two components of Human Resources Planning?

A

Organizational Planning amd Staff Acquisitions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Analogous estimating is also known as?

A

Top-Down Estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost estimating occurs during which of the five process groups?

A

Planning Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the least accurate of all the cost estimating techniques?

A

Top-down estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What cost estimating technique is best to use in the beginning planning stages of any project?

A

Top-down estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is bottom-up estimating?

A

It assigns a cost estimate to each work package on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the most accurate type of cost estimating?

A

Bottom-up estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is work effort?

A

The total time it will take for a person to complete the task if they do nothing else from the time they start until the task is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A work effort estimate is also referred to as a ________________.

A

Person-hour estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In a bottom-up estimate the total cost of each task is figured by multiplying __________ by ____________.

A

Work Effort by Rate

17
Q

What is the Cost Budgeting Process?

A

The process of aggregating all the cost estimates and establishing a cost baseline for the project.

18
Q

What is the cost baseline?

A

The total expected cost for the project.

19
Q

The __________ is used throughout the remainder of the project to measure the overall cost performance.

A

cost baseline

20
Q

The ____________ is used to track the actual expenses incurred against the estimates.

A

Project Budget

21
Q

Project budgets are usually broken down by specific _______________ that are defined by the accounting department.

A

cost categories

22
Q

Salary, hardware, software, travel, training, and materials are examples of __________________ used in project budgets.

A

specific cost categories

23
Q

What is a contingency reserve?

A

a certain amount of money set aside to cover costs resulting from possible adverse events on the project.

24
Q

A contingency reserve is usually a ____________ of the total project cost.

A

percentage

25
Q

What is a management reserve?

A

An amount set aside by upper management to cover future situations that can’t be predicted.

26
Q

The contingency reserve is usually under the discretion of the _______________, while the management reserve is under the discretion of __________________.

A

project manager, upper management

27
Q

Management reserves (are/are not) part of the project budget or cost baseline.

A

are not

28
Q

All future expenditures and variances will be measured against _____________.

A

the cost baseline

29
Q

What is quality planning?

A

the process of identifying quality standards that are applicable to your project and determining how your project will meet these standards.

30
Q

The four most common quality tools and techniques are?

A

Cost-benefit analysis, benchmarking, flowcharting, and cost of quality

31
Q

What is cost of quality?

A

The total cost of all the work required to assure the project meets the quality standards.

32
Q

The three types of costs associated with quality are?

A

Prevention, Appraisal and Failure.