planning for success- scope management Flashcards

1
Q

what is scope and scope management?

A

scope is the totality of the outputs outcomes and benefits and the work required to produce them (this is defining what falls within the project and what doesnt)

scope management - the process whereby outputs outcomes and benefits are defined and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe output, outcome and benefit?

A

output- a product delivered by a project (sale of property)
outcome- the changed circumstance or behaviour that comes from the use of the product (1 less asset on RAP)
Benefit- the positive measurable impact of change (capital receipt)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is an organisation breakdown structure ?

A
  1. shows everyone in project and their roles, reporting lines and communication routes
    2.each role should have a description
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is a responsibility assigned matrix? AKA RACI matrix

A

1.describes the participation of various roles within the project
2.clarifies roles and responsibilities
3. will utilise the roles identified in the organisation breakdown structure

think:
R- responsible
A-accountable
C-those consulted
I-Those informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is configuration?

A

the function and physical characteristics of a product achieved through deployment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is configuration management?

A

the admin activities concerned with the creation, maintenance, change controls and quality control of a scope of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are the 5 configuration management activities

A

1.planning
2. identification
3.control
4.accounting
5.audit