Achieving results- Estimating Flashcards
1
Q
define estimating
A
the use of tools and techniques to forecast data on time and costs of completed work
2
Q
Why do we estimate?
A
- To obtain funding
- To obtain resources
- To assess viability
- To form a basis of control- creates baseline for measuring progress
3
Q
What might estimating during a project lifecycle look like?
A
1.pre- conception. little knowledge of costs +- 50%
2.concept- some understanding +- 30%
3.define - better understanding. high level plan+- 15%
4.deployment- estimates now known +- 10%
5.transition- actual costs known 0%