Achieving results- Estimating Flashcards

1
Q

define estimating

A

the use of tools and techniques to forecast data on time and costs of completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do we estimate?

A
  1. To obtain funding
  2. To obtain resources
  3. To assess viability
  4. To form a basis of control- creates baseline for measuring progress
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What might estimating during a project lifecycle look like?

A

1.pre- conception. little knowledge of costs +- 50%
2.concept- some understanding +- 30%
3.define - better understanding. high level plan+- 15%
4.deployment- estimates now known +- 10%
5.transition- actual costs known 0%