planning for success-Change Control Flashcards
1
Q
what is a change control ?
A
The process where all requests to change the approved baseline of a project are captured and reviewed.
it enable project to assess impact of potential change and make a judgement decision on whether to add them or not.
Change might come from errors, evolution or new policies/governance
2
Q
What is the change control process?
A
CAPTURE>EVALUATE>DECIDED>IMPLEMENT>PROPOSE
3
Q
What must you consider when considering changes to baseline?
A
configuration management!
Any changes to the baseline can have an impact on product spec and characteristics of the product delivered
A change must be controlled