Planning and Scheduling Flashcards
- Which of the following is the proper Design Activity Sequence that is used for every design discipline (such as mechanical, electrical and structural) on a Design/Build logic network according to acceptable legal practices?
A. Engineer, Design, and Build
B. Design, Procurement, and Construction
C. Prepare Schematic Diagrams, Prepare Preliminary Plans, Develop Contract Documents, and Issue Bid Plans
D. Obtain Construction Contract, Request Plans, Receive Plans, Award Subcontracts, Procure Materials, and Construction Activities
C. Prepare Schematic Diagrams, Prepare Preliminary Plans, Develop Contract Documents, and Issue Bid Plans
- Which of the following is the proper Procurement Activity Sequence that is used for every Vendor or Supplier ( such as Rebar, Structural Steel and Sheet Metal) on a Design/Build logic network according to acceptable legal practices?
A. Design, Procurement, and Construction
B. Order and Deliver Materials, Place Forms, Place Rebar, Pour Concrete, and Strip Forms
C. Award Vendor Contract, Vendor Prepares Shop Drawings, Contractor Reviews Shops, A/E Reviews Shops, Vendor Fabricates and Delivers
D. Prepare Design Plans, Award Vendor Contract, A/E Approves Design, Order Materials, Fabricate, A/E Approves Shop Drawings, Contractor Approves Shop Drawings, Vendor Delivers Materials
C. Award Vendor Contract, Vendor Prepares Shop Drawings, Contractor Reviews Shops, A/E Reviews Shops, Vendor Fabricates and Delivers
- Many times the contractor must indicate a sequence of activities as consecutive because of crews or equipment available, What is the term for this sequence called?
A. Restraints
B. Total Float
C. Critical Path
D. Project Duration
A. Restraints
- Leadtimes are used to determine the estimated time durations for what type of activities?
A. Design Activities
B. Procurement Activities
C. Construction Activities
D. Project Closeout Activities
B. Procurement Activities
- How should the nodes on a logic network be numbered?
A. Consecutively
B. Separated by a minimum of five numbers
C. The preceding node is greater than the following node
D. The following node is greater than the concurrent node
B. Separated by a minimum of five numbers
- How is Free Float defined?
A. The amount of slack in a node
B. The amount of slack between acrtivities
C. The amount of slack within a path (series) of activities
D. The amount of slack accumulated throughout the logic network
B. The amount of slack between acrtivities
- What is the name of the term called for shortening a logic network?
A. Crashing
B. Fast tracking
C. Resource Leveling
D. Timed scaled networking
A. Crashing
- What types of activities are considered first when shortening the length of a project?
A. Zero float and least cost
B. Zero float and highest costs
C. Highest floats and least cost
D. High floats and highest costs
A. Zero float and least cost
- What is the primary reason that the courts disfavor a Bar Chart?
A. It displays the activities time scaled
B. It does not show the activity descriptions
C. It displays the interrelationship of activities or the float within activities
D. It does not display the interrelationship of activities or the activity floats
D. It does not display the interrelationship of activities or the activity floats
- How is the term fast tracking defined in construction?
A. Planning and Scheduling the design
B. Overlapping execution of the construction activities
C. Finalizing the design and procurement before construction begins
D. Overlapping execution of the design, procurement and construction
D. Overlapping execution of the design, procurement and construction
- What is the name of the term for shifting the activities within their available free floats in order to produce a uniform work force and reduce the maximum resource usage requirements?
A. Crashing
B. Crew Utilization
C. Resource Leveling
D. Time scaled Networking
C. Resource Leveling
- What is the best source for developing the activity descriptions for the logic network and schedule?
A. General Requirements
B. Technical Specifications
C. Financial Reports and the Balance Sheets
D. Estimate and the Earned Workhour report
B. Technical Specifications
- How is Total Float defined?
A. The amount of slack in a node
B. The amount of slack within an activity
C. The amount of slack within a path (series) of activities
D. The amount of slack accumulated throughout the logic network
C. The amount of slack within a path (series) of activities
- For a Design-Build Schedule to be admissible evidence in court, it must contain the Design Activity Sequence, Procurement Activity Sequence and the Construction Activity sequence. Which of the following must also be on the preliminary schedule?
A. A bar-chart with owner-furnished items and planned weather losses each month
B. A time scaled with owner-furnished items and planned weather losses at the end
C. A bar-chart with planned versus as-built activities, sequence changes & all delays
D. A time scaled with owner-furnished items and planned weather losses each month
D. A time scaled with owner-furnished items and planned weather losses each month