Plan and Acquire Resources Flashcards

1
Q

Which activities does the project manager carry out in terms of managing project resources?

A

Securing critical equipment and infrastructure for the project

Acquiring and supervising the project team

Providing leadership and project management for the duration of a project

Managing physical resources for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which examples are inputs for developing a resource management plan?

A

A lessons learned register

The organizational culture and structure

A high-level project description with requirements

A risk register

The scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the tools and techniques that may be used in the development of a project resource management plan?

A

Organizational theory

Expert judgment

Data representation

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the components of a RACI chart?

A

Inform

Consult

Responsibility

Accountability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which examples represent information that would be included in the roles and responsibilities section of a resource management plan?

A

The designation of project coordinator

Final sign-off on proposed changes to milestone deliverables

The description “to liaise between upper management and the project manager”

The requirement of an in-depth knowledge of the industry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the Estimate Activity Resources process aim to do?

A

Determine the people, materials, equipment, and facilities essential for completing a project

Provide information necessary to draw up the project schedule and budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

You’re managing a project to install a system in an amusement park to monitor the number of visitors per day.

Which types of information do you need to estimate the activity resources for this project?

A

The probability that, given the time of year, bad weather may hamper the installation process

A list of assumptions about the ease and speed of installation of the computerized system

How much the new hardware will cost, as well as labor rates for the installation team

A document outlining the availability of staff members qualified to test and implement the system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which tools and techniques can you use to estimate activity resources?

A

Bottom-up estimating

Meetings

Analogous estimating

Parametric estimating

Expert judgment

Data analysis

A project management information system, or PMIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

You’re managing a highway project. You subcontract various sequential tasks, so scheduling depends on how quickly each team completes tasks.

Using bottom-up estimating, what conclusions do you reach?

A

You determine that you need five ten-person teams, three bulldozers, and three cement mixers for the construction of the four-lane highways

You determine that the teams can share machinery because they will not all be using the same equipment at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the outputs of the Estimate Activity Resources process?
Instruction: Choose all options that best answer the question.

A

The resource breakdown structure

Updates to activity attributes

The resource requirements

A basis of estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

You’re planning an annual newsletter for a social welfare organization and are listing resources the project will need. You use a three-level RBS.

What statements about the project’s RBS are correct?

A

Level one could be titled “Annual newsletter”

Level three could contain nodes titled “Address labels,” “Envelopes,” and “Postage stamps”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which examples are inputs to the Acquire Resources process?

  • The procurement management plan.
  • Procedures regulating staff assignments
  • Resource requirements
  • The market value of resources
A

The availability of potential resources

The resource management plan

Documented policies and guidelines for outsourcing

Resource calendars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which tools and techniques can you use during the Acquire Resources process?

  • Interpersonal and team skills
  • Virtual teams
  • Decision making
  • Preassignment
A

Virtual teams

Negotiation

Preassignment

Multicriteria decision analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the sequence for using negotiation to acquire project resources?

  • Pick the best possible candidates
  • Identify potential barriers
  • Plan your negotiation strategy
  • Negotiate for your team members
A
  1. Picking your “dream team”
  2. Identifying potential barriers
  3. Planning your negotiation strategy
  4. Negotiating for the team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the outputs of the Acquire Resources process?

A
  • Updates to EEFs
  • Project staff assignments
  • Updates to project documents
  • Project management plan updates
  • Resource calendars
  • OPA updates
  • Physical resource assignments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly