Peugeot NQS Flashcards
Before NQS, what was the quality assurance approach of the Peugeot plant?
Poor performance
Problems in the manufactoring
TQS based on mistrust and distrustful operator/controller relationship
What were the key ideas behind the NQS?
Trust in the operator and more responsibilites to the operator (Self-Control). Positive attitude towards work.
Prevention rather than correction.
What were the four main steps of implementing the new management system?
1 Eliminating the roots for errors
2 Monitoring
3 Changes to organizational structures and reponsibilities
4 Changes to the supply system.
What were the key ideas you retained from the case study?
Trust in people
Reducing hierarchy levels yields great benefits
Initial opposition to changes can be overcome