Module 5.1 Knowledge Questions Flashcards
The protective conductor installed on a primary gas meter within 600mm of the meter outlet is known as…
a) a temporary continuity bond
b) a supplementary bond
c) a main equipotential bond
d) an earth bond
c) a main equipotential bond
It is acceptable to use compression fittings on gas ….
a) in suspended timber floors
b) under the screed to a concrete floor
c) where they cannot be seen
d) in accessible locations
d) in accessible locations
The only system of jointing allowed in a protected shaft is…
a) Screwed or welded steel pipe
b) Silver soldered copper joints on copper
c) Soft soldered capillary joints on copper
d) Compression joints on copper
a) Screwed or welded steel pipe
When using soft soldered capillary joints on copper the flux.
a) is not needed
b) should be applied to the pipe ends and the inside of the fittings
c) should be applied to the pipe ends only
d) should be applied to the inside of the fittings only
c) should be applied to the pipe ends only
Gas pipes running vertically behind a dry lining should….
a) only be of corrugated stainless steel
b) be totally encased by adhesive dabs
c) be removed as this is not allowed
d) be jointed with compression fittings
b) be totally encased by adhesive dabs
The regulator on a primary gas meter is….
a) set at 20 mbar
b) set to give a pressure of 21mbar +/- 2mbar
c) of the lead weight type
d) positioned upstream of the emergency control valve
b) set to give a pressure of 21mbar +/- 2mbar
The correct specification for a temporary continuity bond is…
a) not less than 1.2m long, csa 10mm2 of 250v rated single core flexible insulated cable
b) not more than 1.2m long, csa 5mm2 of 450v rated multi core flexible insulated cable
c) not less than 1.2m long, csa 10mm2 of 450v rated multi core flexible uninsulated cable
d) the same as battery booster cables
a) not less than 1.2m long, csa 10mm2 of 250v rated single core flexible insulated cable
Flexible hoses for use on gas cookers are manufactured to…
a) BS 1212
b) BS 1057
c) BS 669
d) BS 864-2
c) BS 669
A medium pressure fed installation is one in which the regulator inlet pressure ….
a) exceeds 21mbar but does not exceed 1 bar
b) exceeds 75mbar but does not exceed 3 bar
c) is lower than that of a low pressure installation
d) exceeds 75mbar but does not exceed 2 bar
d) exceeds 75mbar but does not exceed 2 bar
‘No perceptible loss’ on a water pressure gauge is…
a) when there is absolutely no movement of the meniscus during the tightness test
b) less than 0.25mbar
c) is less than 0.2 mbar
d) 0.5 mbar
b) less than 0.25mbar
The correct sequence for attaching a temporary continuity bond is…
a) Both uninsulated clips to be attached to the pipe at the same time
b) 1st insulated clip to upstream side followed by 2nd insulated clip to downstream side
c) 1st insulated clip to downstream side followed by 2nd insulated clip to upstream side
d) 1st uninsulated clip to downstream side followed by 2nd uninsulated clip to upstream side
b) 1st insulated clip to upstream side followed by 2nd insulated clip to downstream side
The limits for notching of joists to Approved Document A is…
a) min 0.07 x span to max 0.25 x span
b) min 0.25 x span to max 0.07 x span
c) min 0.125 x span to max 0.25 x span
d) min 0.25 x span to max 0.125 x span
a) min 0.07 x span to max 0.25 x span
The correct maximum spacing for clips on a 15mm gas pipe is…
a) 1.8m vertical and 1.2m horizontal
b) 1.8m horizontal and 2.4m vertical
c) 1.5m vertical and 1.8 horizontal
d) 2m vertical and 1.5m horizontal
d) 2m vertical and 1.5m horizontal
Sleeves for gas pipes….
a) can contain a pipe joint
b) must always be sealed both internally and externally at both ends
c) should span the full width of the wall be continuous and sealed internally at one end
d) should be tight fitting and made of steel
c) should span the full width of the wall be continuous and sealed internally at one end
The cross sectional area of a gas pipe duct is 0.08m3 what size of air vent will be required?
a) No air vent required
b) The air vent is always the same as the csa of the duct
c) 0.05m3
d) 1/50th of the cross-sectional area of the duct
c) 0.05m3