module 31- EVM Flashcards

1
Q

Earned Value Management

A

The purpose of an Earned Value Management (EVM) analysis is to determine the current and end of project status of the project with respect to budget and schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value

A

is the total dollar budget of the work that has been completed.

  • measures both schedule and cost performance.
  • the value of work completed to date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Planned Value

A

is the approved budget for work that was scheduled to be accomplished to date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Cost

A

is the total dollar value of costs incurred to date. This includes work and invoices already paid as well as any expenses that have been incurred but not yet invoiced or paid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Budget At completion

A

is the approved total baseline budget approved for the completed project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

50/ 50 rule

A

assigns 50% complete as soon as an activity is started and the activity is considered 100% upon completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

0/100 rule

A

assigns 0% to activities that have not been started and those that are in progress. Completed activities are assigned 100%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Variance

A

compares the difference between the EV and the AC to determine if the project is meeting its budget expectations.
CV = EV − AC”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Variance

A

“compares differences between the EV and the PV to determine if the project is meeting its schedule expectations or if there is a variance.
SV = EV − PV”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost performance Index

A

uses the same inputs as the CV measure but combines them using a ratio that creates a measure of cost efficiency.
CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Performance index

A

“uses the same inputs as the SV measure but combines them using a ratio that creates a measure of time efficiency.
-if greater than one means that the project team is completing more work in less time than expected.
SPI = EV/PV”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To Complete Performance Index

A

the measure of how efficiently the team will need to perform for the remainder of the project in order to meet the baseline budget.
TCPI = (BAC − EV)/(BAC − AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Percent complete index

A

is a measure of how much of the total project work has been completed.
PCIB = EV/BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate TO Complete

A

“provides an estimate of how much money will be needed to complete the project.
ETC = (BAC − EV)/CPI”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimate AT completion

A

“is the new forecast of how much more in total the project is expected to cost once completed.
EAC = AC + ETC”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly