Module 25- Network Diagram Flashcards

1
Q

precedence relationships

A

A project schedule network diagram is a graphical representation of the logical relationships or dependencies the team has recognized during the planning phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Finish to start

A

logical relationship in which a successor activity cannot start until a predecessor has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Finish to finish

A

logical relationship where the successor task cannot be completed until the first task is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Start to Start

A

you cannot start the successor activity until the predecessor activity has started. These relationships are less common and do not occur in the restaurant example.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Start to finish

A

where you cannot end the first task until the second task has started. This is often where there is task dependency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Gantt chart

A

another form of graphically displaying the relationships of tasks. The key stages of a project and their duration are displayed as a bar chart, with the time scale across the top.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Net work diagram

A

A network diagram is a visual depiction that shows the people how the project is organized by task according to when, in what order, and how the activities relate to each other.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly