Module 25- Network Diagram Flashcards
precedence relationships
A project schedule network diagram is a graphical representation of the logical relationships or dependencies the team has recognized during the planning phase.
Finish to start
logical relationship in which a successor activity cannot start until a predecessor has finished.
Finish to finish
logical relationship where the successor task cannot be completed until the first task is completed.
Start to Start
you cannot start the successor activity until the predecessor activity has started. These relationships are less common and do not occur in the restaurant example.
Start to finish
where you cannot end the first task until the second task has started. This is often where there is task dependency.
Gantt chart
another form of graphically displaying the relationships of tasks. The key stages of a project and their duration are displayed as a bar chart, with the time scale across the top.
Net work diagram
A network diagram is a visual depiction that shows the people how the project is organized by task according to when, in what order, and how the activities relate to each other.