Module 26- Critical path Flashcards

1
Q

Float/Slack

A

sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Forward pass

A

this is when you start assigning dates based on the earliest start date, adding dates based on your estimates for each task in the diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Backward pass

A

If you reverse that process and know the required end date of the project, you can start from the end date and do a backward pass. This will show the latest date you can start the project and finish on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

free float

A

Free float is when activities can be delayed without affecting the project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Negative Float

A

Negative float means that the calculated completion of the last activity in the critical path is later than the project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Total Float

A

Total float is the difference between the finish date of the last activity on the critical path and the project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Compression

A

is the reduction of the overall project timeline to the least possible length for the least cost to the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Crashing

A

accelerate the development or progress of (a person or project).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Critical chain

A

adds in the scheduled time buffers to successfully manage the limited resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly