What is the containment average air temperature limit as required in LCO 3.6.1.5 Contaiment Air Temperature?

A

≤ 110 ˚F

Determined by looking at running RCFC inlet temperatures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • LOT 201.01 RCB*
    • *

How are the RCB airlock doors interlocked?

A
  • Personnel Airlock:*
  • *Electronically AND Mechanically Interlocked**
  • Aux Airlock:*
  • *Mechanically Interlocked**

Prevents both doors from being opened at once.

Note:
Interlocks can be defeated when conditions permit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • LOT 201.01 RCB*
    • *

What must IA header pressure to the airlock seals be in order to make the personnel airlock OPERABLE?

A

≥ 90 psig

Cannot decay more than 0.5 psig in 8hrs.

Cannot decay more than 1.5 psig in 24 hrs.

  • Note:*
  • LCO 3.6.1.3 Containment Airlocks is APPLICABLE in MODES 1 - 4.*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • LOT 201.01 RCB*
    • *

Which containment radiation monitor(s) are/is covered by tech specs?

A

RCB Atmosphere Monitor RE-8011A (Particulate)

LCO 3.4.6.1 RCS Leak detection

Applicable in MODES 1 - 4

  • Note:*
  • RE-8011B (Iodine) and RE-8011C (Noble Gas) are non-safety related.*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • LOT 201.01 RCB*
    • *

What will a containment pressure of ≥ 3.0 psig cause?

A

Containment Pressure - High (3.0 psig) [2/3]
Safety Injection
Reactor Trip
Containment Isolation Phase A
Containment Ventilation Isolation
FW Isolation

  • Containment Pressure - High 2 (3.0 psig) [2/3]*
  • *SL Isolation**

Uses PT-934, 935, 936 ONLY

  • Note:*
  • Containment Pressure - High and High 2 are the exact same setpoint….*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • LOT 201.01 RCB*
    • *

What will a containment pressure of ≥ 9.5 psig cause?

A
  • Containment Pressure - High 3 (9.5 psig) [2/4]:*
  • *Containment Spray Actuation**
  • *Containment Isolation Phase B**

Uses PT-934, 935, 936, AND 937

  • Note:*
  • Containment Pressure - High and High 2 use PT-934, 935, and 936 ONLY*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • LOT 201.01 RCB*
    • *

How many emergency sumps are in the RCB?

A

Three

Supplies LHSI, HHSI, and Containment Spray (CS)

  • Note:*
  • Located on RCB -11’ 3”*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • LOT 201.01 RCB*
    • *

What is the design pressure of containment?

A
  • Internal:*
  • *56.5 psig**
  • Between -0.1 and +0.3 psig*
  • CNMT PRESS HI / LOW (CP002)*
  • (LCO 3.6.1.4 Containment Internal Pressure)*
  • External:*
  • *3.5 psig**

Max expected for DBA is 41.2 psig

CNMT PRESS HI/LOW on CP002 will put you in LCO 3.6.1.4 Containment Internal Pressure.

  • Note:*
  • Design temperature is 286 ˚F*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • LOT 201.01 RCB*
    • *

Where are the RCB airlocks physically located?

A
  • Personnel Airlock:*
  • *RCB 68’ SE Quadrant**
  • Aux Airlock:*
  • *RCB 37’ NW Quadrant**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • LOT 201.01 RCB*
    • *

What containment parameters are monitored in the MCR?

A

CP002:
Temperature
Humidity

  • CP004:*
  • *Normal / Secondary Sumps**
  • CP005:*
  • *Personnel Airlock Seals OCIVs**
  • *Airlock Alarms**
  • *Contaiment Pressure Alarms (High / High 3)**
  • *Normal / Secondary Sumps (Alarms)**

CP018:
Pressure Recorder
Hydrogen Recorder

Normal / Secondary Sump Recorder

QDPS / ICS:
Pressure
Radiation (ICS / RM-11 / RM-23)
Normal / Secondary Sumps (QDPS ONLY)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • LOT 201.01 RCB*
    • *

How is the fuel transfer tube sealed for containment purposes?

A
  • RCB Side:*
  • *Double-gasketed blind flange**
  • FHB Side:*
  • *Gate Valve**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • LOT 201.01 RCB*
    • *

Containment is designed to withstand a safe shutdown earthquake (SSE). During such an event, what is the max expected offsite exposure for whole body and the thyroid?

A
  • Whole Body:*
  • *25 Rem**
  • Thyroid:*
  • *300 Rem**

10CFR100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • LOT 201.01 RCB*
    • *

The normal and secondary RCB sumps have how many pumps?

A
  • Secondary Sump:*
  • *1 Pump**
  • Pumps to Normal Sump*
  • Normal Sump:*
  • *2 Pumps w/ alternator**
  • Pumps to Floor Drain Tank (FDT)*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • LOT 201.01 RCB*
    • *

Which radiation monitors feed into PAMS?

A
  • *RE-8050 AND RE-8051**
  • RCB High Range Radiation*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly