Job Information Level 2: Lesson 9 Fire-Resistant Wall and Floor Assembly Penetrations Flashcards
What National Electrical Code (NEC) chapter covers the requirements for firestopping?
Select one:
a.
1
b.
2
c.
3
d.
5
3
A cable assembly that enters a fire resistive wall and exits the opposite side of the wall is considered to be a ? penetration.
Select one:
a.
joint
b.
membrane
c.
passive
d.
through
Through
When penetrating a concrete fire-resistive wall or floor assembly with RMC, it is not acceptable to use mortar to fill the annular space.
Select one:
True
False
False
When a conduit passes through only one side of a fire-resistive wall assembly, it is considered as a ? penetration.
Select one:
a.
joint
b.
membrane
c.
passive
d.
through
Membrane
A listed electrical box for use in fire-resistive assemblies is being installed in a two-hour rated wall. Assuming there are no other electrical boxes on the opposite side of the wall, this installation does not require any penetration protection as long as the annular space between the electrical box and the wall membrane does not exceed ? .
Select one:
a.
1/16”
b.
1/8”
c.
1/4 “
d.
3/8 “
1/8 “
A listed through penetration that identifies a specific manufacturer’s intumescent caulk can be installed using a different manufacturer’s caulk as long as which of the following requirements are met?
Select one:
a.
The caulk has the same ingredients.
b.
The foreman determines it to be suitable.
c.
The complete through penetration has been tested and listed with the different manufacturer’s caulk.
d.
None of the above.
The complete through penetration has been tested and listed with the different manufacturer’s caulk.
Penetrations made in a(n) ? require an L rating with the approved firestop system.
Select one:
a.
firewall
b.
fire partition
c.
smoke barrier
d.
smoke partition
Smoke barrier
During the ASTM E 814/UL 1479 fire test, temperatures may reach as high as ? during a four-hour period.
Select one:
a.
1,700°
b.
1,925°
c.
2,000°
d.
2,300°
2,000°
The temperature requirement that a one-hour fire-resistive assembly must withstand during the ASTM E 814/UL 1479 is ? .
Select one:
a.
1,700°
b.
1,925°
c.
2,000°
d.
2,300°
1,700°
The temperature requirement that a four-hour fire-resistive assembly must withstand during the ASTM E 814/UL 1479 is ? .
Select one:
a.
1,700°
b.
1,925°
c.
2,000°
d.
2,300°
2,000°
The ? rating indicates the length of time (in hours) that the firestop assembly will not exceed 325°F on the unexposed surface during the fire test.
Select one:
a.
F
b.
L
c.
T
d.
W
T
The ? rating indicates the length of time that the firestop system is able to prevent the passage of fire and heat through the opening in an assembly.
Select one:
a.
F
Correct
b.
L
Incorrect
c.
T
Incorrect
d.
W
F
Which of the following is not included in a complete through penetration firestop system?
Select one:
a.
The backing material (mineral wool, insulation etc.)
b.
The fire-resistance rated assembly (wall/floor) materials
c.
The penetrating item (conduit, cable tray etc.)
d.
The sealant (caulk, putty, etc.)
e.
None of the above
None of the above
Wood framed assemblies cannot be classified as fire-resistant assemblies.
Select one:
True
False
False
Through penetrations in concrete floor assemblies can have the annular space filled with mortar provided that the penetrating item is ? .
Select one:
a.
HVAC duct
b.
metallic pipe
c.
PVC pipe (schedule 80)
d.
All of the above
Metalli pipe