ITTO 1 Flashcards
The control costs process has 6 tools and techniques including 1. EVM 2. TCPI 3. Performance reviews 4. Reserve analysis 5. Project mgt software 6.
Forecasting
The estimate activity resources has 8 inputs:
- activity list
- activity attributes
- risk register
- activity cost estimates
What are the other 4?
- Schedule mgt plan
- Resource calendars
- EEFs
- OPAs
The perform quality assurance process has 5 inputs:
- quality mgt plan
- quality metrics
- process improvement plan AND
- quality control measurements
5. project documents
What is the only tool and technique for control scope?
Variance analysis
The sequence activities has 3 tools and techniques:
1. precedence diagramming method (PDM)
AND
- dependence determination
3. leads and lags
The perform quantitative risk analysis process has only one output:
Project documents updates
Identify stakeholders process has 4 inputs:
1. project charter
2. procurement documents
AND
- EEF
4. OPAs
Define activities process has 3 tools/techniques. What are they?
Decomposition
Rolling wave planning
Expert judgment
Requirement documentation IS/ IS NOT an input to identify risks process?
NOT
But it does have 13 inputs.
Control scope has 5 inputs.
1. PM plan
2. Requirements traceability matrix
AND
- work performance data
- requirements documentation
- OPAs
Perform qualitative risk analysis has 1 output. What is it?
Project documents updates
Control schedule process has 6 inputs: 1. PM plan 2. Project schedule 3. work performance data AND
- Project calendars
- Schedule data
- OPAs
The perform quality assurance has 5 inputs: 1. Quality mgt plan 2. quality metrics 3. process improvement plan AND
- quality control measurements
5. project documents
Determine budget process has 9 inputs: 1. activity cost estimates 2. basis of estimates 3. scope baseline 4. project schedule 5. resource calendars 6. agreements AND
- OPAs
- Cost mgt plan
- risk register
The perform quality assurance process has 5 inputs 1. quality mgt plan 2. quality metrics 3. process improvement plan AND
- quality control measurements
5. project documents