The team recently measured technical performance and determine the system was experiencing deterioration at a lower limit than expected. PM updated the risk register to reflect this issue. What process has time just performed?
Control risks
You are the project sponsor. You are considering assigning one of your star performers as PM for the new project. What is your next step?
Develop the project charter yourself.
Changes are/ are NOT called scope creep.
NOT
A PM has been asked to manage a new project. Which task should the PM do first?
Obtain approval for the project charter from the sponsor
Some key stakeholders are actively involved and actively engaging to ensure success of the project. Their level of engagement is
Leading
Nonfunctional requirements fall under which requirements category?
Solution requirements
Taking a documented process from existing OPAs and making changes to it based on the current specific needs of a project is called
Process tailoring
Control procurements process includes
record payment of seller invoice
A tool and technique of manage stakeholder engagement process is
Communication methods
One member wants to remove duration buffers but the other is worried about removing them as it could wipe out the work effort associated with the buffers. Which is correct regarding duration buffers?
Duration buffers are non-work schedule activities
How many WBS levels should there be according to WBS quality principle 1?
WBS Quality Principle 1 does not limit WBS levels
Resource leveling usually causes the project schedule to
Increase
PM found out the vendor was accepting bribes and delivered inferior quality materials. What should PM do immediately?
Report the issue to the appropriate management
The summary milestone schedule is in which document created in project initiation?
Project charter
Define bottom-up ETC
When the original plan is no longer valid, the estimation for the remaining work should be done using bottom-up approach