Deck 4 Flashcards

1
Q

The team recently measured technical performance and determine the system was experiencing deterioration at a lower limit than expected. PM updated the risk register to reflect this issue. What process has time just performed?

A

Control risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You are the project sponsor. You are considering assigning one of your star performers as PM for the new project. What is your next step?

A

Develop the project charter yourself.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Changes are/ are NOT called scope creep.

A

NOT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A PM has been asked to manage a new project. Which task should the PM do first?

A

Obtain approval for the project charter from the sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Some key stakeholders are actively involved and actively engaging to ensure success of the project. Their level of engagement is

A

Leading

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Nonfunctional requirements fall under which requirements category?

A

Solution requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Taking a documented process from existing OPAs and making changes to it based on the current specific needs of a project is called

A

Process tailoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Control procurements process includes

A

record payment of seller invoice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A tool and technique of manage stakeholder engagement process is

A

Communication methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

One member wants to remove duration buffers but the other is worried about removing them as it could wipe out the work effort associated with the buffers. Which is correct regarding duration buffers?

A

Duration buffers are non-work schedule activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How many WBS levels should there be according to WBS quality principle 1?

A

WBS Quality Principle 1 does not limit WBS levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Resource leveling usually causes the project schedule to

A

Increase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PM found out the vendor was accepting bribes and delivered inferior quality materials. What should PM do immediately?

A

Report the issue to the appropriate management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The summary milestone schedule is in which document created in project initiation?

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define bottom-up ETC

A

When the original plan is no longer valid, the estimation for the remaining work should be done using bottom-up approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

During a board meeting, PM is asked to present the business case for the project; instead, PM presents the project charter. What is wrong with this approach?

A

The project charter should not be presented in place of the business case.

17
Q

PM wants to share information to ensure stakeholders understand in the executing phase. Which comm model is most appropriate?

A

sender-receiver model

18
Q

PM just delivered phase deliverable and asked client to provide feedback on project performance. The goal is to provide input for improvement project performance for future phases. What describes the activity being performed?

A

Manage comm process in project communications management

19
Q

What is the difference between configuration control and change control?

A

Configuration control focuses on the specification of both the deliverables and processes while change control focuses on identifying, documenting and controlling changes to the project and product baselines/

20
Q

Process improvement. You are looking for a tool to link the flight delays data with the underlying causes. Which tool will help you focus on the most significant sources?

A

Pareto chart

21
Q

Which analysis method is included in process analysis?

A

Root cause analysis

22
Q

Define fast tracking

A

schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration

23
Q

Which components of the project management plan are specifically considered during the control costs process?

A

cost baseline and cost management plan

24
Q

Calculate cost variance.

A

Earned value minus actual cost

25
Q

Which type of probability distribution represents uncertain values such as durations or schedule activities or costs of project components?

A

Continuous distribution

26
Q

PM wants to terminate the contract for cause and find another vendor to finish the work but learns the vendor unsat was paid in full upon materials delivery. What should be done differently to prevent similar situations?

A

Use of more appropriate contract terms

27
Q

What is a hygiene factor according to Herzberg?

A

Fringe benefits

28
Q

Who is responsible for creating the project charter?

A

Project sponsor

29
Q

The PLan do check act cycle is associated with whom?

A

Deming

30
Q

Suzanne wants to inspect work in process but vendor refuses. What is her best option?

A

Use the contract change control system