Deck 3 Flashcards
What is the difference between control limits and tolerances with respect to quality?
Control limits define the boundaries of common variation and tolerances specify the range of acceptable results.
The project teams uses an Ishikawa diagram and identifies the root cause of the high defect density is due to overly stringent effort estimations. What is your logical next step in this scenario?
Redo the effort estimates with experts
The process of developing options and actions to enhance opportunities and reduce threats to the project objectives is known as
Plan risk response
What are the 7 items in the staff management plan?
Staff acquisition Resource calendars Staff release plan Training needs Recognition and rewards Compliance Safety
Which conflict resolution technique concludes with meeting, discussing at length, long negotiations and parties agree without enthusiasm but with some degree of satisfaction?
Compromise/ reconcile
The project sponsor expresses concerns that some information about certain stakeholders like the classifications are too sensitive and recommends removing this information from the stakeholder register. What to do?
Limit access to the stakeholder classification in the stakeholder register.
Which of the following is not an enterprise environmental factor?
Organizational standard processes and policies.
If deliverables will not be completed in time to go through the control quality process before being inspected by the client, what must the PM do?
Try to move the inspection date because they can’t complete the control quality process prior to the validate scope.
You have completed 40% of your project work. The approved budget is $10,000. How much have you spent to date if your CPI is 0.8?
First calculate the EV and then calculate the AC. EV is calculated using the formula EV = %complete x BAC = 40% x 10,000 = $4,000. AC can be calculated by the formula AC = EV / CPI = $4000/ 0.8 = $5000.
The percentage of defects is very low and you decided that any corrective or preventive action is not necessary. What process should you perform to ensure the customer formally accepts the deliverables?
Validate scope
When a project is in initiation, what should be done immediately if PM learns that the effort involves unknown costs?
Document high level risks related to project costs.
A set of interrelated actions and activities performed to achieve a pre-specified product, result or service is called?
Process
Which of the following documents usually requires the most extensive approval process?
Contract
Strong matrix organizations have many characteristics of a projectized organization with what kind of PM team?
Full-time project management team with considerable authority and a full time project administrative staff.
Which of the following statements regarding the control scope process is not true?
Changes to the scope baseline are approved or rejected during the control scope process