Equations Flashcards
1
Q
Schedule variance (SV)
A
EV - PV
2
Q
Schedule performance index (SPI)
A
EV/ PV
3
Q
Cost variance (CV)
A
EV - AC
4
Q
Cost performance index (CPI)
A
EV/ AC
5
Q
Total cost performance index (TCPI) using BAC
A
(BAC - EV)/ (BAC - AC)
6
Q
Total cost performance index (TCPI) using EAC
A
(BAC - EV)/ (EAC - AC)
7
Q
Variance at completion (VAC)
A
BAC - EAC
8
Q
Estimate TO completion (ETC)
A
EAC - AC
9
Q
Estimate AT completion (EAC)
A
BAC/ CPI
10
Q
Budget at completion (BAC)
A
Sum of all PV