Deck 6 Flashcards

1
Q

Crashing the project requires

A

additional resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Fast tracking is a schedule compression technique in which

A

activities planned to be done sequentially are done in parallel resulting in a shorter project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Resource leveling increases

A

project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Portfolio management is managing projects, programs and other work as a group to

A

meet strategic business objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Procurement negotiations CAN/ CANNOT be started during plan procurement management process

A

NOT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which tool/ technique is most important to the PM during the development of project charter?

A

Expert judgment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which process will PM perform to create the schedule baseline?

A

Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the best place to look for a good reference for a new metric?

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does PM verify that the project deliverable quality is low?

A

With a walk through/ inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If SV is positive, SPI must be

A

Above 1.0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A process is considered out of control if

A

any data point exceeds a control limit or if seven consecutive points are above or below the mean

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a formal method of sending a summary of the approved changes to all stakeholders?

A

Status report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Flowcharts are defined as

A

diagrams of the section of actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fishbone diagrams (ishikawa) are defined as

A

cause and effect diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Decision trees defined as

A

Depicting decisions and aspects of a decision such as utility, probability, cost or outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Influence diagrams are defined as

A

visually depicts risks, decisions, and impacts and how they influence each other

17
Q

What activity ensures the composition of a project’s configuration item is correct and that the corresponding changes are registered, assessed, approved, tracked and correctly implemented?

A

Configuration control

18
Q

Which measurement is the calculated projection of cost performance that must be achieved on the remaining project work to meet a specified management goal?

A

To complete performance index (TCPI)

19
Q

Where would you find project approval requirements?

A

Project charter

20
Q

Cost of conformance includes

A

inspection costs, prevention costs, training, document processes, equipment, appraisal costs

21
Q

Which plan is NOT an input in the identify risks process?

A

Scope management plan

22
Q

Which document does NOT require an approved change request when it is changed?

A

Project charter

23
Q

Crashing is a schedule compression technique that is performed by doing what?

A

allocating more resources or approving overtime. This method is useful when additional resources will shorten the duration of the project.

24
Q

In what process do you perform both resource leveling and modeling techniques?

A

Control schedule

25
Q

According to Maslow’s hierarchy of needs, paying a financial bonus or increasing the salary satisfies the ___ need.

A

safety

26
Q

EEFs are inputs to all processes EXCEPT

A

collect requirements

27
Q

Which of the following statements is NOT true about risks on a project?

A

Risks can only have negative impacts on the project objective

28
Q

What does the “Rule of Seven” refer to for control charts?

A

Seven data points in a row falling on one side of the mean

29
Q

Which forecasting method can be used in the monitor and control process?

A

Scenario building

30
Q

What are three tools and techniques in the develop project team process?

A

interpersonal skills
team-building activities
Recognition and rewards