The develop project team process has 3 inputs. THey are
- project staff assignments
- hr mgt plan
- resource calendars
The critical path method are used when there ARE/ ARE NOT resource limitations.
NOT
Critical chain method is used when
there are buffers, limited resources, project uncertainties
Resource leveling is used to
balance demand
If there is a higher TCPI than a previous CPI, it means
a new project budget was approved
What helps deal with unknown-unknowns?
management reserves
What two processes are performed in the executing process group?
perform quality assurance and develop project team
Name the networking tools for Plan HR MGT process. There are 4.
TRade conferences
Symposiums
Lunch meetings
Informal conversations
Define the two buffers used in the critical chain method
Project buffer: protect target finish date from slippage along critical chain.
Feeding buffer is placed at each point where dependent activities NOT on the critical chain feeds into the critical chain
What are the 3 TT of plan stakeholder mgt?
- expert judgment
- meetings
- analytical techniques
Schedule data IS/ IS NOT an input into the Estimate Activity Durations process
NOT
____ requirements have to be met but in and of themselves bring no specific intrinsic value to the product or service being delivered.
Legal
What does a TCPI > 1 imply?
That future cost performance must be improved in comparison to current performance. The equation represents remaining work divided remaining funds.
What is the WBS quality principle 2?
WBC quality characteristics apply at all levels of scope definition
Name the 3 TT of manage stakeholder engagement
- comm methods
- interpersonal skills
- management skills