Integration Flashcards
What is the purpose of project integration?
Integration means bringing together various factors to form a whole. This process allows you to combine work from all knowledge areas and ensure that resources, deadlines, and the project life cycle are aligned.
What is the role of the project manager during project integration management?
Ensuring due dates of project deliverables, project life cycle and benefits, realization plan or aligned
Providing a project management plan
Ensuring the creation and the use of appropriate knowledge
Managing project performance and changes
Making decisions
Collecting, analyzing and communicating information
Measuring and monitoring progress
Managing transitions
Completing project work
Where are high level strategic and operational assumptions and constraints normally identified?
The business case before the project is initiated and will flow into the project charter.
What is the develop project charter process?
Develop project charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
What is an assumption?
An assumption is a factor in the planning process that is considered to be true, real or certain without proof or demonstration.
What does a project charter include?
Project purpose
Measurable objectives
High level requirements
Assigned resources
Information that will be a key input to the other processes
Which project assets are considered appropriate inputs for the process: develop project charter?
Organizational process assets OPAs
Enterprise environmental factors EEFs
Business documents
Agreements
Which project assets are considered appropriate outputs to be an end result for the process: develop project charter?
Project charter
Assumption log
Which tools and techniques are considered appropriate for the process develop project charter?
Data gathering
Expert judgment
Interpersonal and team skills
Meetings
What are the subsidiary management plans?
Subsidiary management plans include: Scope management plan
Requirements management plan
Schedule management plum
Cost management plum
Quality management plan
Resource management plan
Communications management plan
Risk management plan
Procurement management plan
Stakeholder engagement plan
What is the configuration management plan?
The configuration management planet describes the configurable items of the project and identifies the items that will be recorded and updated so that the product of their project remains consistent and operable.
What is the developed project management plan?
The developed project management plan process defines, prepares and coordinates all plan components and consolidates them onto a single integrated plan
It is the basis of all project work detailing how the project will be executed, monitored and controlled and closed.
Which process group is the developed project management plan process part of?
The developed project management plan process is part of the planning process group and happens at a time in the life cycle when you establish the scope of the project, refine objectives and define how to achieve objectives.
What are the inputs for the developed project management plan?
Enterprise environmental factor
Organizational process assets
Project charter
Outputs from other processes
What is the purpose of direct and manage project work?
This process ensures the team is carrying out the plunder project activities to complete deliverables and that approved changes are made.
Resources are assigned to the work and their time and work is managed.
This process provides overall management for project success.
What are the appropriate inputs for the direct and manage project work process?
Project documents
Enterprise environmental factors
Organizational process assets
Project management plan
Approved change requests
What are the outputs of the direct and manage project work process?
Project document updates
Deliverables
Project management plan of dates
Issue log
Change requests
OPA’s update
Work performance data