Cost Flashcards
What is the budget?
Budget: spreads costs over time, allocating funds to the resources needed to have the project meet its schedule.
What is the contingency reserve?
Contingency reserve: costs of the response solutions for known project risks.
What is the cost baseline?
Cost baseline: the approved version of the time phased project budget excluding any management reserves. It is used as a basis for comparison to actual project results and can only be changed through formal change control procedures.
What is earned value management? (EVM)
A methodology that combines scope, schedule and resource measurements to assess project performance and progress against the project baseline. EVM is one of the best techniques for controlling costs. It helps you understand how you are spending money and what progress is earned for the money spent.
Determining the approximate monetary resources required to complete project activities is the purpose of what project cost management process?
Estimate costs is the process of developing an approximation of the cost of resources needed to complete the project work. The key benefit of this process is that it determines the monetary resources required for the project.
What processes does project cost management include?
Project cost management includes the processes involved in planning, estimating, budgeting, financing, funding, managing and controlling costs so that the project can be completed within the approved budget.
What are the considerations when tailoring processes for project cost management?
Considerations for tailoring project cost management include but are not limited to: knowledge management, estimating and budgeting, earned valued management, use of agile approach and governance.
What is the cost management plan?
The cost management plan defines how the project costs will be estimated budgeted, managed, monitored and controlled. It sets the framework that allows cost processes to be efficient and coordinated.
What are the inputs to the plan cost management process?
Project charter
Project management plan
Organizational process assets
Enterprise environmental factors
What is the output of the plan cost management process?
Cost management plan
What are the tools and techniques for the plan? Cost management process?
Expert judgment
Meetings
Data analysis
What is a cost estimate?
Cost estimate is a quantitative assessment of the likely costs for resources required to complete the activity. Cost estimates are generally expressed in units of some currency and sometimes other units of measure such as staff hours or staff days.
What resources are estimated in cost estimates?
Costs are estimated for all resources that will be charged to the project. This includes, but is not limited to, labor materials, equipment, services and facilities as well as special categories such as an inflation allowance, cost of financing or contingency costs.
What is analogous cost estimating?
Analogous cost estimating uses values, or attributes, of a previous project that are similar to the current project. Values and attributes of the projects may include but are not limited to: scope, cost, budget, duration and measures of scale (eg. size, weight). Comparison of these project values, or attributes, becomes the basis for estimating the same parameter or measurement for the current project.
What is the rough order of magnitude (ROM)?
The rough order of magnitude (ROM) is an estimate of costs provided in the early stages of a project when the scope and requirements are not fully defined. The ROM estimate may have a larger range in the initiation phase (- 25% to 75%) and a narrower range later in the project (-5% to 10%).
What is progressive elaboration?
Progressive elaboration: as the project progresses, the scope will become clearer and estimates will be more accurate.
What is parametric estimating?
Parametric estimating: uses the statistical relationship between historical data and other variables (such as square footage) to calculate a cost estimate. The number of units is multiplied by the cost per unit to derive a cost estimate for that particular entity.
What is bottom-up estimating?
Bottom-up estimating: takes detailed estimates at the work package level to determine the most accurate estimate possible. To begin, estimate the cost of work packages or activities to the greatest level of detail. Then, roll up costs to high levels for reporting and tracking purposes.
What are the inputs to the estimate costs process?
Project management plan
Organizational process assets
Enterprise environmental factors
Project documents