Inspection Interval & Evaluation/ Recording Flashcards

1
Q

If the _______________ of a vessel are changed, the inspection intervals shall be established for the new service conditions.

A

Service Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If both the ownership and the location of a vessel are changed, the vessel shall be __________ and __________ inspected before it is reused.

A

Internally and Externally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When a RBI interval for the internal or on-stream inspections exceeds the 10-year limit, the RBI assessment shall be reviewed and approved by the engineer and inspector at intervals not to exceed __________ or more often if warranted by process, equipment or consequence changes.

A

10 Years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Unless justified by an RBI assessment, each above ground vessel shall be given a visual external inspection at an interval that does not exceed the lesser of __________ years or the required internal/on-stream inspection.

A

Five

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Unless justified by a RBI assessment, a vessel with more than 4 years remaining life shall be inspected _______________.

A

Lesser of Half Life or 10 Years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Unless justified by a RBI assessment, a vessel with 4 years or less remaining life shall be inspected _______________.

A

Lesser of Half Life or 2 Years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

For pressure vessels that are in _______________, the interval is based on the number of years of actual service.

A

Non-Continuous Service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An On-Stream Inspection may be substituted for the internal inspection as long as the general corrosion rate of a vessel is known to be less than __________ per year and remaining life is greater than __________ years

A

0.005 in. per year and 10 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Pressure-relieving devices shall be tested and repaired by a repair organization __________ in valve maintenance.

A

Experienced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Pressure-relieving Device Repair Organizations shall have a fully documented _______________, and fully documented _______________.

A

Quality Control System

Training Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Pressure-relieving devices shall be tested and inspected at intervals that are frequent enough to verify that the valves _______________ in the particular service conditions.

A

Perform Reliably

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Unless documented experience and/or a RBI assessment indicates that a longer interval is acceptable, test and inspection intervals for pressure-relieving devices in typical process services should not exceed:

a. __________ years for typical process services
b. __________ years for clean (nonfouling) and noncorrosive services.

A

a. Five Years

b. Ten Years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Short-term corrosion rates are typically determined by the two _______________ thickness readings.

A

Most Recent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

For corroded area of considerable size the wall thicknesses may be __________.

A

Averaged

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Along a designated length for evaluating LTA, the thickness readings should be __________ spaced.

A

Equally

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Widely scattered pits may be ignored as long as the remaining thickness below the pit is greater than _______________.

A

One-Half the required thickness (1/2 t required)

17
Q

Widely scattered pits may be ignored as long as the total area of the pitting that is deeper than the corrosion allowance does not exceed __________ within any 8-in. diameter circle.

A

7 sq. inches

18
Q

Widely scattered pits may be ignored as long as the sum of the pit dimensions that is deeper than the corrosion allowance along any straight 8-in. line does not exceed __________.

A

2 inches

19
Q

Pressure vessel owners and users shall maintain permanent and progressive __________ of their pressure vessels and pressure-relieving devices.

A

Records

20
Q

Permanent records will be maintained throughout the _______________ of each equipment item.

A

Service Life

21
Q

Pressure vessel and pressure-relieving device records shall contain what four types of information pertinent to mechanical integrity?

A
  1. Construction and Design Information
  2. Inspection History
  3. Repair, Alteration and Rerating Information
  4. Fitness-for-service Assessment Documentation