Inputs and Outputs: Scope Flashcards
List the Inputs: Plan Scope Management
There are 4 Inputs to Plan Scope Management:
1) The Project Charter
2) The Project Management Plan
3) Enterprise Environmental Factors
4) Organizational Process Assets
List the Inputs: Collect Requirements
There are 7 inputs to the Collect Requirements Process:
1) Project Charter
2) Parts of the Project Management Plan (scope/requirements management plans and stakeholder engagement plan)
3) Several project documents (assumptions log, lessons learned/stakeholder registers)
4) Business Docs
5) Agreements
6) EEFs
7) OPAs
List the Inputs: Define Scope
This process requires 5 inputs:
1) Project Charter
2) PM Plan
3) Project Docs (assumption log, requirements docs, risk register)
4) EEFs
5) OPAs
List the Inputs: Create WBS
This process requires 4 inputs:
1) PM Plan
2) Project Docs (Scope Statement and Requirements Docs)
3) EEFs
4) OPAs
List the Inputs: Validate Scope
This process requires 4 inputs:
1) PM Plan
2) Project Docs (in general)
3) Verified Deliverables
4) Work Performance Data
List the Inputs: Control Scope
This process requires 4 inputs:
1) PM Plan
2) Project Docs
3) Work Performance Data
4) OPAs
List the Outputs: Define Scope
This process produces 2 outputs:
1) Project Scope Statement
2) Project Document Updates
List the Outputs: Create WBS
This process produces 1 doc:
1) The scope baseline
List the Outputs: Create WBS
This process produces 4 docs:
1) The scope baseline
2) The WBS
3) the WBS Dictionary
4) Project Document Updates
List the Outputs: Validate Scope
This process produces 4 outputs:
1) Accepted deliverables
2) Work Performance Information
3) Change Requests
4) Project Document Updates
List the Outputs: Control Scope
This process produces 4 outputs:
1) Work performance information
2) Change requests
3) PM Plan Updates
4) Project Document Updates