Q

List the inputs: Develop Charter

A

There are 4 inputs to the Develop Charter process:

  • Business documents (including the method of project selection)
  • Agreements
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List the inputs: Develop Project Management Plan

A

There are 4 inputs to the Develop PM Plan process:

  • Project Charter
  • Outputs from other processes (plans)
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List the inputs: Direct and Manage Project Work

A

There are 5 inputs to the Direct and Manage Project Work process:

  • PM Plan
  • Project Docs
  • Approved Change Requests
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List the inputs: Manage Project Knowledge

A

There are 5 inputs to the Manage Project Knowledge process:

  • PM Plan
  • Project Docs
  • Deliverables
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List the inputs: Monitor and Control Project Work

A

There are 5 inputs to the Monitor and Control Project Work process:

  • PM Plan
  • Project Docs (including assumption log, basis of estimates, cost forecasts, issue log, lessons learned register, milestone list, quality reports, risk register, risk report, and schedule forecasts)
  • Work Performance Information
  • Agreements
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

List the inputs: Perform Integrated Change Control

A

There are 6 inputs to the Perform Integrated Change Control process:

  • PM Plan
  • PM Docs
  • Work Performance Reports
  • Change Requests
  • EEFs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

List the inputs: Close Project/Phase

A

There are 8 inputs to the close project/phase process:

  • Project Charter
  • PM Plan
  • Project Documents
  • Accepted Deliverables
  • Business Docs
  • Agreements
  • Procurement Docs
  • OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the outputs: Develop Charter

A

There are 2 main outputs to Develop Charter:

  • The project charter
  • The assumption log
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List the outputs: Develop Project Management Plan

A

There is only one output to the Develop PM Plan process: the Project Management Plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List the outputs: Direct and Manage Project Work

A

There are 3 main outputs to Direct and Manage Project Work:

  • The deliverables
  • Work Performance Data
  • The “Issue Log”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

List the outputs: Manage Project Knowledge

A

There is only one output to the Manage Project Knowledge process: The lessons learned register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

List the outputs: Monitor and Control Project Work

A

There are 2 main outputs to the monitor and control project work process:

  • Work Performance Reports
  • Change requests
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

List the outputs: Perform Integrated Change Control

A

There are 2 main outputs to the perform integrated change control process:

  • Approved change requests
  • Updates to project documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

List the outputs: Close Project/Phase

A

There are 4 main outputs to the close project/phase process:

  • the final product
  • the final report
  • service/result transition
  • project document updates