Inputs and Outputs: Schedule Flashcards
1
Q
List the inputs of Plan Schedule Management
A
There are 4 inputs to the Plan Schedule Management process:
- the project charter
- the PM Plan
- EEFs
- OPAs
2
Q
List the inputs of Define Activities
A
There are 3 inputs to the Define Activities process:
- the PM Plan (specifically the schedule management plan and the scope baseline)
- EEFs
- OPAs
3
Q
List the inputs of Sequence Activities
A
There are 4 inputs to the Sequence Activities process:
- the PM Plan (specifically the schedule management plan and the scope baseline)
- Project Documents (specifically the activity list, activity attributes, milestone list, and the assumption log)
- EEFs
- OPAs
4
Q
List the inputs of Estimate Activity Durations
A
There are 4 inputs to the Estimate Activity Durations process:
- the PM Plan (specifically the schedule management plan and the scope baseline)
- Project Documents (specifically the activity list, activity attributes, resource requirements, resource calendars, and resource breakdown structure)
- EEFs
- OPAs
5
Q
List the inputs of Develop Schedule
A
There are 5 inputs to the Develop Schedule process:
- the project charter
- the PM Plan (specifically the schedule management plan and the scope baseline)
- Project Documents (specifically the activity list, activity attributes, assumption log, basis and duration of estimates, lessons learned, milestone list, schedule network diagrams, team assignments, resource calendar and requirements, and the the risk register).
- Agreements
- EEFs
- OPAs
6
Q
List the inputs of Control Schedule
A
There are 4 inputs to the Control Schedule process:
- the PM Plan
- Project Documents (specifically the lessons learned register, project/resource calendars, project schedule, and schedule data).
- Work Performance Data
- OPAs