Formulas Flashcards

1
Q

BAC (Budget at Completion)

A

No formula, see approved budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV (Planned Value)

A

(% time completed) x (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV (Earned Value)

A

(% work completed) x (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC (Actual Cost)

A

No formula, $ amount spent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV (Cost Variance)

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV (Schedule Variance)

A

SV = EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI (Cost Performance Index)

A

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPIc (Cumulative Cost Performance Index)

A

CPIc = EVc/ACc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SPI (Schedule Performance Index)

A

SPI = EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC (Estimate At Completion)

A

EAC = BAC/CPIc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

ETC (Estimate To Completion)

A

ETP = EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

VAC (Variance At Completion)

A

VAC = BAC-EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TCPIc (To Complete Performance Index)

A

TCPIc = (BAC-EV)/remaining funds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

BCR (Benefit Cost Ratio)

A

BCR = expected value/expected cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EVA (Economic Value Add)

A

EVA = after tax profits - (capital invested x cost of capital)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

NPV (net present value)

A

NPV = present value - cost of the project

*note that present value is sometimes represented as PV (same as planned value).

17
Q

ROI (Return on Investment)

A

ROI = (Benefit - Cost) / Cost

18
Q

ROIC (Return on Investment Capital)

A

ROIC = Net income after tax / total capital invested

19
Q

Beta Distribution

A

Beta Distribution = (pessimistic + 4(realistic) + Optimistic) / 6

20
Q

Triangular Distribution

A

Triangular Distribution = (pess. + real + opt) / 3

21
Q

EMV (Expected Monetary Value) / Decision Tree Analysis

A

EMV = probability x value

Could have multiple probabilities, which would result in multiplying all probabilities by the value.