Inputs and Outputs: Resource Flashcards
List the inputs: Plan Resource Management
This process requires five inputs:
1) Project Charter
2) PM Plan
3) Project Documents
4) EEFs
5) OPAs
List the inputs: Estimate Activity Resources
This process requires 4 inputs:
1) PM Plan
2) Project Docs
3) EEFs
4) OPAs
List the inputs: Acquire Resources
This process requires 4 inputs:
1) PM Plan
2) Project Docs
3) EEFs
4) OPAs
List the inputs: Develop Team
This process requires 4 inputs:
1) PM Plan
2) Project Docs
3) EEFs
4) OPAs
List the inputs: Manage Team
This process requires 6 inputs:
1) PM Plan
2) Project Docs
3) Work Performance Reports
4) Team Performance Assessment
5) EEFs
6) OPAs
List the inputs: Control Resources
This process requires 5 inputs:
1) PM Plan
2) Project Docs
3) Work performance data
4) Agreements
5) OPAs
List the outputs: Plan Resource Management
This process produces 3 outputs:
1) Resource Management Plan
2) Team Charter
3) Project Document Updates
List the outputs: Estimate Activity Resources
This process produces 4 outputs
1) Resource Requirements
2) Basis of estimates
3) Resource Breakdown Structure
4) Project Document Updates
List the outputs: Acquire Resources
This process produces 8 outputs:
1) Physical resource assignments
2) Project Team assignments
3) Resource calendars
4) Change requests
5) PM Plan Updates
6) Project Document Updates
7) EEF Updates
8) OPA Updates
List the outputs: Develop Team
This process produces 6 outputs:
1) Team performance assessments
2) Change requests
3) PM Plan Updates
4) Project Docs Updates
5) EEF Updates
6) OPA Updates
List the outputs: Manage Team
This process produces 4 outputs:
1) Change requests
2) PM Plan updates
3) Project Document Updates
4) EEF Updates
List the outputs: Control Resources
This process produces 4 outputs
1) Work performance information
2) Change requests
3) PM Plan updates
4) Project document updates