Inputs and Outputs: Resource Flashcards

1
Q

List the inputs: Plan Resource Management

A

This process requires five inputs:

1) Project Charter
2) PM Plan
3) Project Documents
4) EEFs
5) OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List the inputs: Estimate Activity Resources

A

This process requires 4 inputs:

1) PM Plan
2) Project Docs
3) EEFs
4) OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List the inputs: Acquire Resources

A

This process requires 4 inputs:

1) PM Plan
2) Project Docs
3) EEFs
4) OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List the inputs: Develop Team

A

This process requires 4 inputs:

1) PM Plan
2) Project Docs
3) EEFs
4) OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

List the inputs: Manage Team

A

This process requires 6 inputs:

1) PM Plan
2) Project Docs
3) Work Performance Reports
4) Team Performance Assessment
5) EEFs
6) OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

List the inputs: Control Resources

A

This process requires 5 inputs:

1) PM Plan
2) Project Docs
3) Work performance data
4) Agreements
5) OPAs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

List the outputs: Plan Resource Management

A

This process produces 3 outputs:

1) Resource Management Plan
2) Team Charter
3) Project Document Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the outputs: Estimate Activity Resources

A

This process produces 4 outputs

1) Resource Requirements
2) Basis of estimates
3) Resource Breakdown Structure
4) Project Document Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

List the outputs: Acquire Resources

A

This process produces 8 outputs:

1) Physical resource assignments
2) Project Team assignments
3) Resource calendars
4) Change requests
5) PM Plan Updates
6) Project Document Updates
7) EEF Updates
8) OPA Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

List the outputs: Develop Team

A

This process produces 6 outputs:

1) Team performance assessments
2) Change requests
3) PM Plan Updates
4) Project Docs Updates
5) EEF Updates
6) OPA Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

List the outputs: Manage Team

A

This process produces 4 outputs:

1) Change requests
2) PM Plan updates
3) Project Document Updates
4) EEF Updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

List the outputs: Control Resources

A

This process produces 4 outputs

1) Work performance information
2) Change requests
3) PM Plan updates
4) Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly