G-2 ICI Flashcards

1
Q
  1. Design for formwork for concrete
A

safety
architectural design
type of concrete member being cast
efficiency
environmental conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Tall architectural concrete wall
A

rate of placement will have to be moderate and the stud spacing close

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Sub-grade is important to what formwork.
A

slab-on-ground

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Increase formwork efficiency
A

Use modular panel sizes, uniform tie spacing, and prefabricated components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Required the strongest forms
A

Columns require the strongest forms because they are often tall and the concrete is placed all in one placement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Carry the load of fresh concrete + equipment
A

Falsework

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Temperature falls while placing concrete
A

Rate of placement should be reduced if temperature falls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Formwork pressure -factors
A

Dependent on the rate of placement and the rate at which the concrete gains strength

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Concrete slump
A

The slump of the concrete is a measurement of the concrete’s consistency. Low slump concrete is stiff and had to work, high slump will be fluid and easy to place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Type of form to make/create a textured face
A

specialized formwork or

sandblasted and tooled concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Architectural concrete designed with max deflection in formwork
A

1/400 Canadian max deflection 1/360 American standard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. BCBC Requirements on air temperature
A

mortar shall be used and placed in final position
a) within 1.5 h after mixing when the air temperature is 25°C or higher, or
b) within 2.5 h after mixing when the air temperature is less than 25°C.