Foundations of Planning Flashcards

1
Q

Elements to be Planned

A
  • deliverables (quality)
  • dates (time and end date)
  • resources (people and budget)
  • work (what first - most important)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Plan - Purposes

A
  • Guides project execution
  • Provides baseline for progress measurement and project control
  • Easier communication among stakeholders
  • Eliminate or reduces uncertainty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Plan

A
  1. A document that describes the technical and managing approach to be followed for a project
  2. The plan typically defines
    - work to be done
    - resources
    - methods
    - procedures
    - schedules
    - organization
  3. The project plan is central and important!
    - measure the progress
    - formal and approved
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Baseline

A
  1. The originally approved plan plus or minus approved changes
  2. Baselines are used
    - to compare the actual performance
    - to give forecasts of the project with the original plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Activities

A
  1. An element of work performed during the course of a project. An activity normally has expected duration, an expected cost and expected resource requirements
  2. Activity decomposition
    - Activities are recursively decomposed into sub-activities
  3. Atomic activity (work package)
    - not further decomposed
    - performed by one or a few people in a short time
    - with well-defined inputs and outputs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Work Package

A
  1. An activity that can be executed within a short time
  2. Delivers a clear result that can be checked against its requirements
  3. Work package
    - result & intermediate results
    - final and intermediate deadlines
    - effort and duration estimation
    - actual cost (when finished)
  4. A contract between project manager and developer
  5. Basis for estimation of effort, controlling, and workload balancing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Milestone

A
  1. Milestones are defined points in time during the project where defined results have to be available
  2. External milestone
    - Gate with a go / no-go decision
    - The customer decides based on the results and the market situation
  3. Internal milestone
    - Milestone between external milestones
    - Used for internal controlling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Product Breakdown Structure (PBS)

A
  • Hierarchical structure of things that the project will make or outcomes that it will deliver
  • Decomposes a Main Product into its constituent parts in the form of a hierarchical structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Work Breakdown Structure (WBS)

A
  • A deliverable-oriented, hierarchical grouping of project elements that organizes and defines the total work scope of the project.
  • Each descending level represents an increasing detailed definition of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Validating a WBS

A
  1. Disjunction rule
    - All activities of a level must be completely distinct
  2. Completion rule
    - If an activity is decomposed in sub-activities the whole scope of the activity must be converted
    - Nothing is left
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Checklist for WBS Work Packages

A
  1. Can we estimate cost and duration?
  2. Can we measure the progress?
  3. Can the task of the work package be performed independently from other work packages?
    -> no coordination between work packages is needed!
How well did you know this?
1
Not at all
2
3
4
5
Perfectly