Foundations of Planning Flashcards
1
Q
Elements to be Planned
A
- deliverables (quality)
- dates (time and end date)
- resources (people and budget)
- work (what first - most important)
2
Q
Project Plan - Purposes
A
- Guides project execution
- Provides baseline for progress measurement and project control
- Easier communication among stakeholders
- Eliminate or reduces uncertainty
3
Q
Project Plan
A
- A document that describes the technical and managing approach to be followed for a project
- The plan typically defines
- work to be done
- resources
- methods
- procedures
- schedules
- organization - The project plan is central and important!
- measure the progress
- formal and approved
4
Q
Baseline
A
- The originally approved plan plus or minus approved changes
- Baselines are used
- to compare the actual performance
- to give forecasts of the project with the original plan
5
Q
Activities
A
- An element of work performed during the course of a project. An activity normally has expected duration, an expected cost and expected resource requirements
- Activity decomposition
- Activities are recursively decomposed into sub-activities - Atomic activity (work package)
- not further decomposed
- performed by one or a few people in a short time
- with well-defined inputs and outputs
6
Q
Work Package
A
- An activity that can be executed within a short time
- Delivers a clear result that can be checked against its requirements
- Work package
- result & intermediate results
- final and intermediate deadlines
- effort and duration estimation
- actual cost (when finished) - A contract between project manager and developer
- Basis for estimation of effort, controlling, and workload balancing
7
Q
Milestone
A
- Milestones are defined points in time during the project where defined results have to be available
- External milestone
- Gate with a go / no-go decision
- The customer decides based on the results and the market situation - Internal milestone
- Milestone between external milestones
- Used for internal controlling
8
Q
Product Breakdown Structure (PBS)
A
- Hierarchical structure of things that the project will make or outcomes that it will deliver
- Decomposes a Main Product into its constituent parts in the form of a hierarchical structure
9
Q
Work Breakdown Structure (WBS)
A
- A deliverable-oriented, hierarchical grouping of project elements that organizes and defines the total work scope of the project.
- Each descending level represents an increasing detailed definition of the project
10
Q
Validating a WBS
A
- Disjunction rule
- All activities of a level must be completely distinct - Completion rule
- If an activity is decomposed in sub-activities the whole scope of the activity must be converted
- Nothing is left
11
Q
Checklist for WBS Work Packages
A
- Can we estimate cost and duration?
- Can we measure the progress?
- Can the task of the work package be performed independently from other work packages?
-> no coordination between work packages is needed!