Earned Value Analysis Flashcards
1
Q
Earned Value Analysis?
A
- A method to measure the amount of work actually performed
- A method to forecast a projectʼs total cost and date of completion, based on trend analysis
- Is a snapshot in time and used as an early warning system
- Work Scheduling Efficiency
- Comparison of the actual duration the work is completed to the planned duration - Work Cost Efficiency
- Comparison of the actual cost of the completed work to the planned cost - Relies on the key metric known as earned value
2
Q
Planned Value (PV)
A
- The planned budget for work currently scheduled
- Budget at completion is the estimated total cost
3
Q
Actual Cost (AC)
A
Total cost incurred for the project up to a specified date:
- Actual Cost of Work Performed (ACWP)
- Contains both direct and indirect cost
4
Q
Earned Value (EV)
A
- The sum of planned cost for the work completed
- Budgeted Cost of Work Performed (BCWP) - EV represents the value of the completed work expressed in terms of the budget assigned to that work
5
Q
CPI / SPI Interpretations
A
- CPI > 1: The cost of work performed is lower
- CPI = 1: Project is in budget
- CPI < 1: The cost of work is higher; project is over budget
- SPI > 1: Project is ahead of schedule
- SPI = 1: Project is in schedule
- SPI < 1: Project is behind schedule
-> Around 1 -> Well managed project
6
Q
EVA - Metrics
A
- PV: How much work should be done?
- EV: How much work was done?
- AC: How much did the work cost?
- CPI: Is the project in budget?
- SPI: Is the project in schedule?
- EAC: What do we expect the total project to cost?
7
Q
EVA - Steps
A
- Determine EV, PV, and AC
- Calculate CV and CV
- Calculate CPI and SPI
- Calculate the forecast for the project costs EAC
- Calculate the forecast for the project duration EDP
- Interpret the calculated key figures
- Control your project
8
Q
EVA - Prerequisites
A
- The project must be fully planned
- The project must be structured into a sufficient number of acttivities
- Each activity must have a
- cost estimate
- a planned start date
- a planned finish date - The effort recoding must be structured according to activities and must take place immediately
9
Q
EVA - Advantages
A
- The method is clearly defined, simple, and fully tracable
- It makes projects comparable with each other in terms of cost and schedule adherence
- It allows forecasts to be made of
- expected costs when the project is completed
- expected end date
10
Q
EVA - Disadvantages
A
- The complete implementation of the method is not easy
- It requires an environment / organization with a high degree of project maturity
- It is only applicable to projects with clearly defined requirements / deliverables