Final exam - Chapter 14 Flashcards

1
Q

Scheduling

A

Scheduling

refers to the assignment of start and completion times to particular jobs, people, or equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

•Sequencing

A

•Sequencing

refers to determining the order in which jobs or tasks are processed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

First come first server

Sequencing or Scheduling

A

Sequencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sequencing is used in what sector

A

service sector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s a good example that the teacher talked about for sequencing

A

Walmart line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Staff scheduling problem:

A

Staff scheduling problem:
Given minimum worker requirements for each day of the week, schedule employees so that each has two consecutive days off and all demand requirements are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Method:

2

A

Method:

  1. Locate the set of at least two consecutive days with the smallest requirements, circle the requirements for these days, & assign a worker to all days not circled.
  2. Subtract 1 from the requirement of each day not circled, removing existing circles, and repeat this process until all requirements are satisfied.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

learn how to do slide 6 in chapter 14

A

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Difference between flow time and make span (test question)

A

flowtime - how much time it takes to make one unit

Make span - how much time it takes to make one batch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lateness

A

Lateness is the difference between the completion time and the due date (either positive or negative).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Tardiness

A

Tardiness is the amount of time by which the completion time exceeds the due date. (Tardiness is defined as zero if the job is completed before the due date, and therefore no credit is given for completing a job early).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Lateness and tardiness measure

A

Lateness and tardiness measure performance related to customer-focused due-date criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Two of the most popular sequencing rules for prioritizing jobs are:

A

Two of the most popular sequencing rules for prioritizing jobs are:
Shortest Processing Time (SPT)

Earliest Due Date (EDD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Shortest Processing Time (SPT)

A

Shortest Processing Time (SPT)
With different processing times, SPT sequencing maximizes resource utilization and minimizes average flow time and WIP inventory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Earliest Due Date (EDD)

A

Earliest Due Date (EDD)

Earliest Due Date (EDD), minimizes the maximum job tardiness and lateness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Other Sequencing Rule

A

First come-first served (FCFS).

17
Q

How do we use the shortest processing time?

A
  • Whichever have the shortest processing time you are going to process that first
  • you are ignoring due date information
  • minimize flowe time and w/i/p
18
Q

What is the problem with the shortest processing time

A
  • the late processing time can be never completed since it takes too much time to process
  • a lot of TARDINESS
19
Q

Earliest due date:

A

you process whatever that is due first

20
Q

what is the problem with the earliest due date

A

it may block the short processing time products from being processed

21
Q

In a serial manufacturing process, a bottleneck workstation controls the output of the entire process. Thus, it is critical to schedule it efficiently.

A
  1. When processing times are relatively equal, first-come-first-served sequencing works well.
  2. With different processing times, SPT sequencing maximizes workstation utilization and minimizes average job flow time.
  3. Using Earliest Due Date (EDD), the maximum job tardiness and lateness are minimized.
22
Q

learn slide 12 - 15 (math shit) test question

A

-

23
Q

Two-Resource Sequencing Problem (Johnson’s Rule)

A
  1. List the jobs and their processing times on Resources #1 and #2.
  2. Find the job with the shortest processing time (on either resource).
  3. If this time corresponds to Resource #1, sequence the job first; if it corresponds to Resource #2, sequence the job last.
  4. Repeat steps 2 and 3, using the next-shortest processing time and working inward from both ends of the sequence until all jobs have been scheduled
24
Q

learn slide 17, 18 (math shit) test question

A

-