Extensions of time Flashcards

1
Q

What clause is extensions of time dealt with?

A

2.20 Relevant events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a relevant event?

A

Variations

CAI

Deferment of possession

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When must contractor give notice?

A

When it becomes reasonably apparent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When have you experienced a delay?

A

On Ldubs for the plant deck remediations?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you assess the plant deck delay was appropriate for an extension of time?

A

The contractor provided a delay notice

I then undertook a ‘Critical Path Analysis’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What method did you use for the delay analysis and are there alternatives?

A

Critical Path

There is also

  • Overview of facts
  • Comparing actual and planned progress
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did you undertake the critical path analysis?

A

I analysed the works which were critical to completion using Microsoft Project.

The logic link between the the new plant deck and the reinstatement/replacement of plant was estimated two months and an additional month was included due to the consultant work required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the advantageous of using the critical path analysis?

A

Using software (Micro Project) allowed dynamic reactions on impact of delay. For instance, I can enter extensions of time onto critical pathways quickly and accurately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly