Case study Flashcards
Can you name other procurement routes?
Design and build
Management procurement
Why did your client not opt for traditional procurement competitive tendering?
Early contractor involvement required
Client required price surety
Competitive tendering would increase time requirements and client wanted work done ASAP
Are there time and cost implications using competitive tendering?
Yes design would need to be complete and the design and construction cannot overlap.
Competitive pricing can be an advantage however greater time is required.
How did you ensure the level of was pricing was satisfactory for negotiating the tender?
Once submitted the price was negotiated by the project qs.
What information does the project qs use for pricing “?
Bcisand in house rates
What is a pre construction agreement and why was this utilized?
This is allows the client to employ the contractor prior to the contract. It enables significantly more contractor collaboration for elements of the design.
What are the advantages of using a pcsa?
Construction risk decreases as the contractor uses their specific knowledge to improve build ability
Why was the intermediate contract chosen over minor works?
Allows collateral warranties Allows a pcsa Greater control procedures Allows sectional completion Allows partial possession
What other consultants were appointed on the contract?
Hoare lea Plymouth m&e consultants
T&g engineers
What were the services provided by the structural engineer?
Scaffold fixings, some were missing and the o and Marion did not have information on lateral loadings. They tested this.
They also provided ser services for the fire ducts and later the louvre screening and also the design for the new roof.
What formed the contract documentation for the project?
Jct intermediate contract with cdp with amends for jersey law
Bhp contract drawings
Bhp preliminaries
Hoare lea basement car park ventilation specification
Ac Mauger priced tender
What documents were provided to the contractor detailing the design?
Hoare lea basement car park ventilation specification for tendering to their sub contractor. This formed their cdp portion. Also bhp speciation
What is the governing health and safety legislation in jersey? What was the effect on the project?
Management in construction jersey 2016
Defines project as a major project Required a hspc Requires pcsi Requires healthy and safety file Hspc also approves construction phase plan and prepares a f9 notice
What was the flat roof finished with and what were the defects?
Sika single ply adhered to insulation
This was de bonded
Spoiled with no routine maintenance
Approximately 100 tears leading to water ingress
What is a Granite Rain Screen?
Cladding attached to primary structure
Forms ventilated system
LW4 was ventilated