Construction Technology and Environmental Services Flashcards

1
Q

What is the sequence of operation of strip foundation?

A

Top soil removed

ground levels reduced

earth work support

Steel reinforcement and concrete laid

Bricks or concrete inserted (to conform with BS 5628 if below ground)

Superstructure transition at ground level.

DPC at 150mm above ground level

Cavity wall to be at least 50mm

Wall tie spacing at 900mm centres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is piling and name and explain two types?

A

Series of columns inserted into ground to transmit point loads.

Used in soils with low load bearing capacity.

Loads are distributed different to raft or strip (large area distribution).

Different types
End Bearing Piles - transmit load to firm strata

Friction Piles - transmit loads to surrounding soil via friction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What effect does ACOP 8 have on projects?

A

Depends on the project.

Is building built prior the ban of asbestos?

Does the building require licensed or un-licensed Asbestos removal?

Both have the potential to inflate cost, licensed more.

If Asbestos is to remain in situ considerations need to be given training to persons accessing site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What effect does Management in Construction have on cleaning windows?

A

Design specification should give consideration to safe cleaning (for instance cleaning from the inside). Or potential abseiling points.

Any remaining risk needs to be captured in a risk register.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What consideration were given to the approved document ‘Structure’ in regard to the replacement at Windward House?

A

Compared loading (old and new)

Reviewed O&MS and cross reffed with insulation in-situ.

The wholesale replacement would have been Kingspan closed cell insulation. This was significantly heavier than the existing open cell insulation and I am aware that an engineers inspection/recommendation would be needed to assess if strengthening measures were required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What drainage provisions were required for Windward?

A

As the works turned into a patch repair remediation no drainage works were required. Although, I understand guidance is at

Document 6 - Drainage, hygiene and hot water storage, as well as relevant BS guidance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

For Windward, (Warm Deck) how did you prevent potential interstitial condensation?

A

Warm roofs have less chance of interstitial condensation than cold roofs.

Specifying adequate insulation and VCL should prevent air within voids reaching dew point.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What were the cost difference with the options put towards your client on Windward House?

A

Full roof remediation - $720,000

Patch repair - $170,000

Both exclude professional fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why were the contract works for full roof remediation more expensive over patch repairs?

A

Full roof remediation required scaffold and canopy (longer time frame and associated risks).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

For Windward, what was the difference in quality for patch repair and full remediation?

A

Full remediation included - material warranties, collateral warranties.

Patch repair did not have warranties on materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

On Windward, Did you provide your client advise on the sensitivities of the works?

A

Yes, Major roof repairs would be significantly louder and risked the potential for water ingress if no canopy was used. This would be detrimental to the top floor tenants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Are there any tests you can undertake to identify routes of water entry within a single ply membrane?

A

Dry Testing (sends DC current across membrane)

Wet Testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you explain advantages and disadvantages of timber frame over blockwork regarding time?

A

Timber;
faster.
Internal finishes can applied earlier
Can be watertight quicker

Concrete blockwork
More time consuming to lay
Greater degree of skill (longer procurement time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain advantages and disadvantages of timber frame regarding cost?

A

Cost of materials is roughly the same albeit timber can yield lower costs as the installation time is faster.

Long term structural defects are common in my experience so the reducing of cost for construction may not be a long term benefit. Good standard of design or monitoring is crucial for both however.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Explain advantages and disadvantages of timber frame regarding quality?

A

Concrete block is fire resistant by default, although with appropriate spec timber can achieve appropriate levels of fire resistance.

Timber frames need quality materials, installation and weatherproofing to maintain longevity.

Timber frames need to be teated to protect against mould, rot and damp whereas concrete block work does not.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In brick walls describe sequence of operation for wall ties?

A

Spaced at 600mm centres at each 3 courses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Name some types of pointing?

A

Bucket handle
Fluch
Overhung

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Describe sequence of operation of a cavity wall?

A

Mass concrete foundation (depending on strata)

Bricks and blocks below ground (bs stand)

Cavity below ground filled with weak concrete (prevents earth moving pressure)

DPC 150mm above ground level

Note; cavity to extend 225m belo DPC

Wall ties at 900mm centres 450 apart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Describe the sequence of operation of a solid floor on level site?

A

Insulated screed and floor finish

DPM

Solid concrete bed compacted over hard core

cavity wall to extend 225mm below DPC

weak cement in cavity below 225m to resist compressive pressure from backfill.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Describe the sequence of operation of a suspended timber floor?

A

flooring

Insulation

Joists (at 400mm centres)

DPC

Sleeper wall

100mm thick concrete atop well compacted hardcore

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Name two types of floor structures?

A

Suspended timber floor

Solid floor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Discuss the sequence of operation of a standard purlin roof?

A
Ridge board
Rafters at 400 centres
Purlin at 1600 centres
Collar fixed to purlin
Hangars stemming from collar to joists 
Joists
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is a roof truss and what is its sequence of operation?

A

These are triangulated roof frames designed to give clear spans between the external supporting walls. They are usually prefabricated. (Study Page 398/399 in Chudley and Greeno)!!!!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a roof underlay?

A

barrier for wind driven rain between slates and tiles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the build up of a roof above the rafters on a typical timber pitched roof?

A

Top down

tilling 
tile battern
counter bettern
VCL 
Rafters
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What primary legislation governs planning legislation?

A

Town and country planning act 1990

Planning (Listed Buildings and Conservation Areas) Act 1990

27
Q

Explain Part 11.2B in relation to roof replacement?

A

For roofs which require replacement of 50% or more in the whole roof areas requires replacement in accordance with latest regulations.

28
Q

Why did the riser enclosures need to comply with document part 11.2B? (Conservation with fuel and power)

A

They didn’t because they were not habitable, of which i advised my client. However the justification to the enclosures was to ensure longevity to the control panels. If the internal temp was consistently dropping below to dew point interstitial condensation could have occurred. Appropriate insulation prevents this.

29
Q

What did the feasibility assessment include for the roof remediation to Windward house?

A

Planning requirements

Environmental Impacts

Statutory approvals

Analysis of client requirements

Assessment of potential existing facilities (LW4 preliminaries)

Material Options and programme

Procurement options

30
Q

What was the clients KPI for Windward remediation?

A

Cost - cheap as possible

Time - as quick as possible to meet project timeline

31
Q

What were the disadvantages you advised your client on regarding short term remediation to Windward House?

A

No material Warranties
Lower quality of work
Potential to disrupt tenant in the short term to perform wholesale repair

32
Q

On Windward House, why did you advise your client to proceed with a negotiated tender?

A

Because their tenant was moving in in two months, the works need to be complete ASAP. The negotiated tender allowed design and construction to overlap which significantly reduce time frame for completion.

33
Q

Why were warranties important to Windward House and why did you advise your client that none would be present?

A

Ensure quality, however as time and cost were at the forefront the warranties were not as crucial.

34
Q

L1 - How do self cleaning windows work?

A

Hydrophic and hydrohilic coatings

35
Q

L1 - what would you class as a low maintenance roof?

A

flat roofs for large roof areas as cleaning is easier.

Materials such as EPDM appear to have better lifecycle over bituminous felts.

On smaller pitched roofs materials such as slates require more on going maintenance

Inverted roofs

36
Q

L1 - If a ceiling required 60 minutes fire protection how would it need to be constructed?

A

joists of 35mm at 600 centres

2 x 12.5mm fire rated plaster board (e.g siniat or gyproc)

37
Q

L1 - How might a 30 minute fire resisting partition wall be constructed?

A

Stud (no insulation) - 9mm fire boads each side of the timber stud wall, studs at 600mm centres.

38
Q

L1 - Where might am inverted roof be used?

A

Protection - areas with severe ultraviolet light or extreme temps

Performance - areas that need additional sound insulation

Areas which require a ‘giving back to nature’ approach. Green roofs in cities for instance.

39
Q

L1 - Are there disadvantages to singly ply membranes?

A

Easily punctured

Seams are vulnerable to leaks

UV rays degrades membrane

Roofing accessories

40
Q

L1 - Why might a single ply roof be used over a felt covering?

A

In areas with high foot fall

Architectural projects (aesphetics)

Reliable installation (if warranted0

41
Q

L1 - What is a raft foundation

A

Continous slab resting on soil that extends weight over entire footprint. Used in soil with poor bearing capacity.

42
Q

L1 - What are the pros and cons of steel frames?

A

pros

  • Strength
  • easy fabrication
  • moisture and weather resitance

cons

  • thermal conductivity
  • reduced flexibility on site (no changes)
  • supporting structure (drywall etc) can increase time - resulting in higher costs
43
Q

L1 - What are the pros and cons of concrete frames?

A

pros

  • high compressive strength
  • fire protection by default
  • weather resistance
  • low maintenance

cons

  • tensile strength to compressive (reinforcement)
  • high form costs
  • high embodied energy
  • shrinkage
44
Q

L1 - How might a basement be waterproofed?

A

Three methods
1-Dense monolithic walls and floors
2-Tanking
3-Drained cavity

RICS SEMINAR

45
Q

L1 - other than piled and raft what foundations have you worked with?

A

strips (go deeper on this!)

46
Q

L2 - At windy, if the whole roof needed to be replaced what were the requirements?

A

U value of 0.18w/(m2.k)2

110mm Kingspan insulation

NB: this considers the roof membrane, the way it is adhered, and the roof structure.

47
Q

L2 - roof construction at Windy?

A

reinforced concrete roof

48
Q

L2 - what were the minimum requirements for compliance with regs for windy?

A

wholesale replacement -

  • U value - 0.18 m2k2
  • Air permeability requirements
  • document B fire
49
Q

L2 - Did you have to consult with any design guidance for the roof?
Bathy
Windy
LFDC

A

Bathy
-Historic England ‘Insulating pitched roofs’ for design guidance for the cold roof

Windy

  • BRE Digest 324 Flat room design (Thermal Insulation)
  • manual of low slope roof systems

LFDC
- BRE Digest - natural and manmade slates

50
Q

L2 - What services were in the risers?

A

Two types of risers

Dry risers (for fire fighting)

51
Q

L2 - How were compartment floors or walls stoped within the risers?

A

!

52
Q

L2 - What compliance with doc 11.2 was required (at windy)?

A

The new insulation roof system required a u-value of 0.18.

53
Q

L2 - What compliance with the Island Plan impacts the roof at Windy?

A

If more than 50% of the roof covering is being replaced then the whole roof areas, including the insulation to the whole roof, is required to be replaced and upgraded to modern regs of 0.18.

54
Q

L2 - Were there design standards the risers needed to comply with?

A

!

55
Q

L3 - At Windy, what was your advice in relation to an appropriate short term remediation?

A

To patch repair but to undertake eletrical survey of the roof to identify all leaks.

Also to undertake electrical test upon completion.

In addition, conduct appropriate routine maintenance to the single ply membrane to prevent build up of debris and prevent teh likelyhood of it falling into poor repair.

56
Q

L3 - At Windy, how long did you expect the short term remediation to extend the lifespan of the roof?

A

The roof was in poor repair because it had lifted and was torn. If this could be prevented it had the potential to have a lifecycle of 5 years. Albeit because no warranties/gaurantees were being provided i had to advise my client that this could not be 100% gauranteed.

57
Q

L3 - Did you attempt to advise your client that a longer term remediation option might be more appropriate?

A

Yes and i also advised that via visual inspection the plant on the roof was in significantly high level of poor repair and full replacement of the roof (M&E and covering) would serve as a valued approach.

I also advised that the benefit of the long term remediation would be collateral warranties and product guarantees which could serve as comfort for their tenants for re-gearing of their leases.

58
Q

L3 - Were you able to consider a solution and advise your client that still allowed the new tenant to occupy the fifth floor while works were undertaken?

A

Speed on site and a negotiated tender was advised. I further advised of the implications of using this approach.

We have two months to get on site and complete prior to the new tenant moving in. The Contractor had advised that we needed 6 weeks to complete the works.

59
Q

L3 - What was your advice relating to the patch repairs? How was this to be undertaken?

A

?

60
Q

L3 - At Ldubs, what impact did the block work or timber solutions have on the roof structure and how did this impact on your advice to the client?

A

Block work had additional weight

Timber not so much

EXTEND ON THIS !!!!

???????

61
Q

L3 - How did you propose that the timber enclosure would be constructed to offer support for the louvre system that you refer to?

A

I proposed to omit the louvre system to the sides. I liaised with planning officer who advised me that this was permitted.

62
Q

L3 - When looking at the timber or block work options, did you consider the weather protection of the service within the enclosure?

A

The idea was to improve the protection of the services. The enclosures provided this. I further considered and advised my client that using the single-ply membrane to waterproof the enclosures would be sufficient to protected against water ingress.

63
Q

DO MORE L3 ON THIS and apply the questions to other jobs

A

!!!!