Contract Administration Flashcards
What are the certificates in the Intermediate contract? (5)
1 - Interim Certificate 2-Certificate of making good defects 3-Certificate of practical completion 4 - Final Certificate 5-Certificate of non-completion
What is the process for making good defects? (3)
1-These should be notified by the CA/Archi to the Contractor
2-The CA should issue a schedule within 14 days of PC.
3- When CA is satisfied all defects are made good only then can ‘Certificate of making food defects’ be made.
What is the criteria for Practical Complete? (2)
1-Practical Completion of the works is achieved
2-contractor has sufficiently complied with clause 3.18 (supply of information required for Health and Safety File’.
What is the procedure for PC in the Intermediate contract?
There is no procedure it is however for the CA to issue the certificate i the criteria for PC is met.
What is the procedure if practical completion is not met?
The CA must issue certificate, this is a prerequisite for deduction of Liquidated Damages.
Once certificate is issued the contractor is in ‘Culpable Delay’.
When are Liquidated Damages claimed and how?
Subsequent interim valuation or reclaim sum as debt.
What are the preconditions for claiming Liquidated Damages? (4)
1-Contractor failed to complete works by date of completion
2- CA must have issued cert for non completion
3-CA must have fulfilled all duties with respect to the award of an extension of time
4-Employer must give contractor written notice of its intention prior date of final cert
Why would a CA issue CAI?
1 - Discrepancies in contract docs
2- Variations
What are the five underpinning requirements to create a contract?
1-Offer 2-Acceptance 3-Consideration 4-Mutual Obligation 5-Competency and Capacity
What is traditional Procurement?
Design and construction is separate
Full documentation provided to contractor at RIBA stage 4.
Competitive tender process
Independant CA
Valuation/Payment obligated by employer
What are the advantages of traditional procurement?
Certainty of design
Clarity on project requirements
flexibility through variations
What are the disadvantages of traditional procurement?
Slow commencement
No contractor involvement for complex build issues
What is design and build?
Contractor is responsible for both design and construction of work in return for a lump sum
What are the advantages of Design and Build?
Speed as design and construction overlaps
Early start on site
Increased cost control
Increased time control
What are the disadvantages of Design and Build?
Contractor may exploit quality
Design variations have significant cost and time implications
When is the Intermediate Contract Suitable?
When works are simple
When works are designed on behalf of the employer
Where CA/Archi is required to monitor the works
Where partial possession/sectional completion required
Where collateral Warranties are required
What are the clients key drives?
cost
time
quality
What was the clients key driver for Liberation House remediation?
Quality
In relation to a JCT contract, what mechanisms impact on time?
relevant events
What is a relevant event?
Incidents which can create a delay for a contractor who can then be entitled to an extension of time. (e.g impediment by the client / late information from consultant).
Why is it important that a contractor gets an extension of time?
Mitigate LADs
Additional costs to the contractor (prelims, labour)
Name some relevant events?
Variations
CAI
Impediment by employer
Exceptionally Adverse weather
In relation to relevant events, what is ‘Deferment of Possession’?
This is when the client does not handover site on contracted date.
L1 - You note that the contractor was not paid on time, what is this called and what is process the contractor can apply in this situation?
Suspension by contractor (if contractor has not been paid by employer)
Contractor must notify CA/Archi
Not paid within 7 days he can suspend the works.
If that causes a delay he is entitled to an extension
For LW4 you note that the deflection caused the works to stop? What contractual mechanism deals with this?
Relevant events - Variation / impediment by employer
What is the process if the contractor is in delay?
Notice in writing (recorded delivery)
Sent when it becomes ‘reasonable apparent’
Identify relevant event
Is there a time bar on relevant event claims?
No only when it becomes reasonably apparent - they can be late but it is good practice to have these done early
What should the CA do if it receives notice of contractors extension of time request?
Give if reasonable notify contractor give reasons within 12 weeks State extension of time relating to each relevant event Fix new completion date
What are liquidated Damages and are these penalties?
pre determined loss a client would incur as a result of project completing late - this is not a penalty
Are liquidated damages a penalty?
No
What is a payment notice?
Informing contractor of payment value (within 5 days)
What is a lay less notice?
Deduction for poor workmanship or overvalued valuation.
What are the three ways valuations of variations can be carried out?
1-Quotation clause
2-Measure & Price
3-Daywork’s Clause
If you were building a tower block and the ground floor external paving blocks (50 pound per meter) were to used at the roof garden (decided as a variation), which way would this be valued?
Measure and price - Pro rata (adjust rate for additional labour / remove rubble, etc).
What pricing method was applied to the additional works at Liberation House?
Measure and price (no prices in bills of quants therefore there was a build up of first principles).
What is a relevant matter?
Relevant events caused by the client. The client must pay loss and expense.
How is loss and expense calculated?
This is ascertained, it is not in a pricing book it is actual money in which the contractor is out of pocket. This excludes profits.
What is the process for loss and expense?
1-Contractor makes application as soon as apparent
2-Archi/CA instructs QS to ascertain
3-Contractor provides further info and QS ascertains loss and expense
What is the process for instructions under JCT contracts?
1-Archi/CA issues verbal instruction
2-Contractor confirms in writing to CA within 7 days
3-If CA does not reject in seven days it stands
Tell me about opening up to check work? Who has responsibility for paying?
If works are not to standard contractor pays
If works are correct the client pays
What are the main consequences of practical completion?
Possession of site reverts to employer Employer must not insure works First part of retention is released Rectification period begins Contractors Liability to LADS ceases Contractor has 6 months for final account
Advise the client on requirements of a valid contract?
1-Offer
2-Acceptance
3-Consideration
For a 5M pound project what JTC contract is suitable and why?
JTC standard Building Contract
Traditional Procurement - quality
Regarding remediation works to 43 Bath Street your client questions why you did not advise Design and Build? He seeks pros and cons.
It does have higher levels of price surety
1-Listing/Historic implications
2-Design and Build has less control over
quality
3-Client has les control over building work with D&B
During the works to LW4 you instructed additional works to the riser enclosures, how were these works valued?
Measure and price and build up of fair principles.
For the additional single ply membrane to Liberation House, how was the single ply valued?
Existing bills of quantities.