Exam 4 prep Flashcards
Sec chem b/d, PW, CW, TC, NC, EC, WC
State when SG BD valves will close automatically?
All containment isolation valves close on SAM
o SIAS
o AFAS
o MSIS
What will happen to the SG BD system on CSAS?
CSAS or Loss of PKA
IA to containment has isolated
▪ 500R & P fail close and blowdown isolates
▪ To restore:
• Must take both valves to override and closed position
• Then override and open IA-UV-2 to restore IA to containment.
• This prevents re-initiating blowdown uncontrollably
Where are the BD sample line points?
What cools the sample lines and at what point in the system?
Blowdown sample line points
o Hot leg blowdown
o Downcomer blowdown line
o Directly from downcomer blowdown
▪ NC cools field coolers and WC cools the cold lab sample lines
▪ Sample lines are upstream of blowdown isolation valves to allow sample even if blowdown flow isn’t from that path
Why is the D/C line the normally and preferred aligned flowpath?
Promotes efficiency of blowdown process
What component cannot accomodate any Hi Rate B/D, or both SG’s @ abnormal rate?
the BFT.
How is BFT pressure maintained normally?
Alternately?
WHy is 4A isolated on power changes => 5%?
Pressure maintained by 2 valves:
▪ Normally: 4A which directs flow to the HDT equalizing line
• Must keep pressure > 150 psig to maintain D/P to prevent back flow from the equalizing line to the condenser
▪ Alternately: 4B which opens to maintain pressure to the condenser
• 4B opens when 4A is unable to maintain setpoint pressure
▪ When changing power by 5% 4A is isolated to prevent a chemistry excursion
How is BFT level maintained by the following?
DEMIN/RETIN LV 3B/3C
BYP DEMIN
Level is maintained by HS-3
▪ DEMIN/RETIN LV 3B/3C
• Controls BFT level by sending flow to the blowdown demin package.
▪ BYP DEMIN
• Controls BFT level by sending flow to the #3 LPFW shells
What must occur on a high temperature at the B/D demins?
the system isolates flow to the B/D Demin package.
The operator MUST take the handswitch to BYP DEMIN to allow level in the BFT to be controlled and prevent relief valve lifting
Where do the B/D Low TDS sump pumps discharge to?
Where can they also discharge to?
Discharge to CW return line
o Can also discharge to the CWNTs and LRS TDS system
What is the heat sink for the BD HX?
Condensate cooled.
When is blowdown routed directly to the condenser?
BFT Not available.
HI Rate BD
< 25% pwr with long path recirc secured.
when it is desired to use condensate demins instead of BD demins.
Unit is operating normally with blowdown aligned to the BFT, when a SIAS occurs. Chemistry has requested the ability to sample 1 SG. What actions are required to get this sample?
SGBD sample lines will close on SIAS. Must take the sample isolations to override.
What are the starting interlocks associated with the CW pump discharge valves?
CW pump discharge valves:
-
1st pump start IN A LOOP
- Pump starts and its associated pump discharge goes to 44% open
-
2nd pump start IN A LOOP
- pump starts and disch valve goes to 44%.
- waits for 3 min and then goes to 100%, after 2nd pump discharge goes 100% then the 1st pump valve goes to 100%
-
1st pump stopped IN A LOOP (with 2 pumps running)
- Pump switch to stop, associated discharge valve goes to 8% open, the associated pump will trip, and discharge valve full closes. Discharge valve is interlocked closed for 2 min
- Discharge valve of the 2nd pump auto closes to 44% if the cross-tie valve is full open AND only 1 CW Pump is running in the other loop or cross-tie is not FULL open.
How will UV-11 respond to a loss of all running CW pumps in a loop?
UV-11 will auto close when there are no running pumps in a CW loop.
If taken to open then UV-11 will open regardless.
What will block a CW pump start? How is this bypassed?
The associated loop condenser outlet valve closed will block CW pump start in that loop.
Can bypass with pushbutton on B07.
what must be met to open the CW Condenser outlet valves?
Pressure switches must indicate that the waterboxes are full.
What cools the CW pump bearing and motor lube oil coolers?
TC
What are the limits on CW pump operations with respect to the number of towers in operation?
With 1 tower in operation, only 1 CW pump can be run. WIth 2 towers, up to 2 CW pumps can be operated.
What happens to the HI vibration trip of the CW tower fans on fan start?
It is bypassed for 30 seconds.
Describe what makes up the A train and B train with respect to the CW system and the hotwells
“A” Train (NAN-S01) = A&B CW pumps, 2A/2B/2C hotwells, A cond pump, HV-10
“B” Train (NAN-S02 = C&D CW pumps, 1A/1B/1C hotwells, C cond pump, HV-9
What is the design dT across the condenser?
32F dT
What is the position of the CW pump discharge valves and cross-tie valve(HV-11) with >=3 pumps operating?
100% open.
State the normal and alternate PW return points.
Normal is the Main CW return line.
Alternate is to Tower 2.
How is canal level contrlled? Why is proper canal level important?
A controller provides makeup as necessary to maintain level. This prevents short circuit of the cooling tower and adequate pump suction.
What is the purpose of the circulating water system?
A. acts as the ultimate heat sink for safe reactor shutdown and long term core decay heat removal.
B. receives the heat rejected by the turbine cycle and plant cooling water system and dissipates it to the cooling towers for removal by evaporation.
C. acts as both the ultimate heat sink for safe reactor shutdown and long term core decay heat removal AND receives the heat rejected by the turbine cycle, plant cooling water and dissipates it to the cooling towers.
D. removes heat from the plant cooling water system ONLY and dissipates it to the cooling towers.
B. receives the heat rejected by the turbine cycle and plant cooling water system and dissipates it to the cooling towers for removal by evaporation.
How is CW system piping initially filled on startup?
Using the PW system. It can withstand drawing initial vacuum in the condenser.
Concerning the CW Condenser inlet and outlet valves, what is prevented from operating if these valves are closed? How long of a stroke time do they have?
CW pumps won’t start if Condenser outlet valves are closed. They have a 60 sec. stroke time.
What will automatically close Cross tie valve(HV-11)?
If both CW pumps in a loop are stopped, HV-11 will auto close. This causes CW SYS TRBL in the cr.
Describe what happens to pump disch valves as each pump is started on system startup.
- 1st CW pump start in Loop - pump starts and discharge valve opens to 44%
- 2nd CW pump start in Loop – pump starts and discharge valve opens to 44%,
- 3 min TD, 2nd discharge valve to 100%, 1st discharge valve to 100%.
State the CW pump start permissive interlock that must be met prior to pump start; this interlock exists for ___________.
A. Cooling tower return valve closed; prevent lifting waterbox relief.
B. associated train Condenser outlet valve open; prevent lifting waterbox relief.
C. Cooling tower return valve closed; water hammer concerns
D. associated train Condenser outlet valve open; water hammer concerns
D. associated train Condenser outlet valve open; Water hammer concerns.
State what happens when the first CW pump in a loop is stopped.
What does this prevent?
On pump stop:
- that pump disch valve starts to close.
- At 8% open, the associated pump trips and the valve finishes closing.
- This disch valve is interlocked closed for 2 min.
- Following pump stop, the running pump discharge valve in the SAME loop will auto close to 44% if:
- The cross tie valve is not full open OR
- The cross tie valve is full open AND only 1 pump is running in the other loop.
- Prevents runout of the running CW pump in the loop.
How is an operator alerted to a CT fan HI VIbration trip?
a blue light at the loadcenter, computer input and alarms in the CR.
What is the start sequence for CT fans?
Fans started/stopped in sequence
Sequence found in 40OP-9CW03 see attached picture.
Outer ring fans started before inner ones.
Started or stopped one at a time.
Alternate between in-service cooling towers for each fan start or stop.
What systems or components does PW cool?
What cools PW?
Cools NC HX, TC HX, and Air Removal vacuum pump seal coolers
Fills CW, screen wash for CW
Heat removed by CW/cooling towers.
State the operating characteristics of the PW pumps.
- 50 psig
- 75°F
- 29,000 gpm
State the minimum canal level needed to operate PW pumps. What is prevented by maintaining this level.
19’ minimum canal level prevents air binding of the PW pump.
What auto starts are associated with the PW pumps?
What trips exist?
Low hdr pressure of 40psig. amber light will be lit.
Will trip on electrical protection and Load Shed.
When will the PW pumps restart following a restoration of power?
the pump that is GREEN FLAGGED will auto start after 20 seconds.
State what will give a PCW SYS TRBL and PCW DSCH PRESS HI-LO
PCW SYS TRBL - Pump A/B Electrical Protection Trip OR Not In Auto/ Not Running
PCW DSCH PRESS HI-LO - 58 psig / 40 psig
Where does the PW system return to CW?
Normally, it is returned to directly to CW header
Alternate return is CT # 2.
Unit is at 100% power and experiences a loss of PW. What major plant action is directed by Loss of CW AOP?
The reactor/turbine must be tripped immediately.
A 86 lockout has occurred on the A PW pump. Can this lockout be reset from the CR?
NO.
State the Auto starts associated with the TC pumps.
TC pumps will auto start on low pressure < 55psig.
What will happen to the TC pumps during a loss of power to the non class buses?
They will be load shed and the TC pump that is green flagged will restart 15 seconds after power is restored if TC pressure is < 55psig.