EVM Flashcards

1
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Formula for Earned Value.

A

% Complete x Budget at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Performance Index (CPI) formula.

A

Earned Value / Actual costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Performance Index (SPI) formula.

A

Earned Value / Planned Costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does a CPI or SPI less than 1 mean?

A

Project is behind. SPI - will be late. CPI - will be over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost variance (CV) formula.

A

Earned Value - Actual Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule variance formula.

A

Earned Value - Planned costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Formula for Final project cost or Estimate at Completion (EAC).

A

Budget at Completion / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Formula for Final project duration.

A

Planned project duration / SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why would you use EVM?

A

-How well project is doing against time and cost.
-Find areas of under-achievement.
-Provides information to aid decision making.
-Quantifies performance variances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the benefits of EVM?

A

-Consistent reporting.
-Provides information to aid decision making.
-Plot trends to indicate the direction of the project.
-Tolerances/Thresholds can be set to enable management by excepion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly