EVM Flashcards
Formula for Earned Value.
% Complete x Budget at Completion
Cost Performance Index (CPI) formula.
Earned Value / Actual costs.
Schedule Performance Index (SPI) formula.
Earned Value / Planned Costs.
What does a CPI or SPI less than 1 mean?
Project is behind. SPI - will be late. CPI - will be over budget.
Cost variance (CV) formula.
Earned Value - Actual Costs
Schedule variance formula.
Earned Value - Planned costs.
Formula for Final project cost or Estimate at Completion (EAC).
Budget at Completion / CPI
Formula for Final project duration.
Planned project duration / SPI
Why would you use EVM?
-How well project is doing against time and cost.
-Find areas of under-achievement.
-Provides information to aid decision making.
-Quantifies performance variances.
What are the benefits of EVM?
-Consistent reporting.
-Provides information to aid decision making.
-Plot trends to indicate the direction of the project.
-Tolerances/Thresholds can be set to enable management by excepion.