Is it permissible to have a mixed final sub-circuit supplying lights and socket outlets on a construction site?
No - they must be on separate circuits.
AS/NZS 3012 Clause 2.1.6.
What is the maximum permissible length of 2.5mm?, 15A three core sheathed extension cord which may be used on a construction site?
40m.
AS/NZS 3012 Clause 2.6.7 Table 1.
What is the maximum length of flexible cord supplying relocatable premises on a construction site?
15m.
AS/NZS 3012 Clause 2.9(b).
Which clause in AS/NZS 3012 specifies the frequency requirements for the inspection and testing of equipment used on construction sites?
AS/NZS 3012 Clause 3.2 Table 6.
What is the minimum permissible height at which festoon lighting may be supported above any floor on a construction site according to AS/NZS 3012?
2.5m.
AS/NZS 3012 Clause 2.7.6 (c)
Is it mandatory to maintain a record of inspections and tests conducted on relevant equipment on a construction site? Give the AS/NZS 3012 Clause number.
Yes.
AS/NZS 3012 Clause 3.9.