Earned Value Management System (EVMS) Flashcards

Learn the principles of earned value

1
Q

SOW is?

A

Statement of Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

WBS is?

A

Work Breakdown Structure

What work is to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What kind of account is used to accumulate costs?

A

Control account
or
Cost account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

All tasks that will charge to a control account are called a?

A

A work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

All tasks in a work package are planned in a detailed _____ ?

A

Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A WBS can be viewed as an org chart and breaks down what?

A

The work to be performed into explicit areas and sub-areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an OBS?

A

Organizational Breakdown Structure

Tells WHO is responsible for the work to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a RAM?

A

A Responsibility Assignment Matrix.

Typically, Control accounts are matrixed to facilitate accumulation of costs by both task and performing organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define BAC

A

Budget at Completion – it is our target

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC is?

A

Estimate To Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC is?

A

Estimate At Complete

Sum of ACWP + ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BAC is?

A

Budgeted At Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

VAC is?

A

Variance at Completion

BAC - EAC = VAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

TRUE / FALSE :

Both Cost Tracking and Performance Measuring are provided by EVMS

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

BCWS

A

Budgeted Cost of Work Scheduled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

BCWP

A

Budgeted Cost of Work Performed

17
Q

ACWP

A

Actual Cost of Work Performed

18
Q

EVMS is a system that helps you do what four tasks?

A
  1. Evaluate Performance
  2. Predict where you are going
  3. Estimate what is needed to successfully complete the project
  4. Minimize Risk of Project Failure
19
Q

Cost Variance CV is calculated how?

favorable is positive

A

CV = BCWP - ACWP

CV% = CV / BCWP

20
Q

Schedule Variance SV calculated how?

favorable is positive

A

SV = BCWP - BCWS

SV% = SV / BCWS

21
Q

Variance at Completion (VAC) calculation?

favorable is positive

A

VAC = BAC - EAC

22
Q

Cost Efficiency – CPI calculated how?

favorable is > 1.0

A

CPI = BCWP / ACWP

23
Q

Schedule Efficiency – SPI calculated how?

favorable is > 1.0

A

SPI = BCWP / BCWS

24
Q

Percent Complete calculation?

A

BCWP cum / BAC

25
Q

Percent Spent calculation?

A

ACWP cum / BAC

26
Q

To Complete Performance Index (TCPI) calculation

A

TCPI cum = Work Remaining /
Cost Remaining

           = BAC - BCWP cum  / 
              EAC - ACWP cum
27
Q

Estimate at Completion CPI

A

EAC cpi = BAC / CPI cum

28
Q

Estimate at Completion Composite

A

EAC comp = ACWP cum +
BAC - BCWP cum /
(CPI cum) * (SPI cum)