EARNED VALUE FORMULAS & OTHERS Flashcards

1
Q

PV = FV / (1 + R) ^n

=FUTURE VALUE / (1 + INTEREST RATE)^ # OF PERIODS

A

PRESENT VALUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

CV = EV - AC

=EARNED VALUE - ACTUAL COST

A

COST VARIANCE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPI = EV / AC

=EARNED VALUE / ACTUAL COST

A

COST PERFORMANCE INDEX

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SV = EV - PV

=EARNED VALUE - PRESENT VALUE

A

SCHEDULE VARIANCE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

SPI = EV / PV

=EARNED VALUE / PRESENT VALUE

A

SCHEDULE PERFORMANCE INDEX

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

EV = (COMPLETION % )(PV)

= (COMPLETION %)(PRESENT VALUE)

A

EARNED VALUE (A)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EV = (CPI)(AC)

= (COST PERFORMANCE INDEX)(ACTUAL COST)

A

EARNED VALUE (B)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EAC = ETC + AC

=ESTIMATE TO COMPLETION + ACTUAL COST

A

ESTIMATE AT COMPLETION (A)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC = EV / CPI

= EARNED VALUE / COST PERFORMANCE INDEX

A

ESTIMATE AT COMPLETION (B)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC = AC + BOTTOM UP ETC

=ACTUAL COST + BOTTOM UP ESTIMATE TO COMPLETION

A

ESTIMATE AT COMPLETION (C)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC = BAC / CPI

= BUDGET AT COMPLETION / COST PERFORMANCE INDEX

A

ESTIMATE AT COMPLETION (D)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EAC = AC +(BAC - EV)

= ACTUAL COST + (BUDGET AT COMPLETION - EARNED VALUE)

A

ESTIMATE AT COMPLETION (E)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC = AC + [(BAC - EV) / (CPI*SPI)]

= ACTUAL COST + [(BUDGET AT COMPLETION - EARNED VALUE) / (COST PERFORMANCE INDEX * SCHEDULE PERFORMANCE INDEX)]

A

ESTIMATE AT COMPLETION (F)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

TCPI = (BAC - EV) / (BAC-AC)

= (BUDGET AT COMPLETION - EARNED VALUE) / (BUDGET AT COMPLETION - ACTUAL COST)

= REMAINING WORK / REMAINING FUNDS

A

TO COMPLETE PERFORMANCE INDEX

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

ETC = EAC - AC

= ESTIMATE AT COMPLETION - ACTUAL COST

A

ESTIMATE TO COMPLETION (A)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

ETC = (BAC - EV) / CPI

= (BUDGET AT COMPLETION - EARNED VALUE) / COST PERFORMANCE INDEX

A

ESTIMATE TO COMPLETION (B)

17
Q

VAC = BAC - EAC

= BUDGET AT COMPLETION - ESTIMATE AT COMPLETION

A

VARIANCE AT COMPLETION

18
Q

FLOAT CAN BE CALUCATED WITH WHICH 2 FORMULAS ?

A
LATE START - EARLY START
LS - ES 
OR
LATE FINISH - EARLY FINISH
LF - EF
19
Q

THE SUM OF THE COSTS THAT HAVE ALREADY BEEN EXPENDED

20
Q

EMV = (%)(-X)

ESTIMATED MONETARY VALUE

A

EMV IS CALCULATED AS THE PROBABLE TIMES OF IMPACT.
EXAMPLE: 50% CHANCE OF RAIN AT A COST OF $10,000
EMV OF (50%)(-10,000) = $5,000