DIVISION 4 QUESTIONS Flashcards

1
Q

IN PROJECT MANAGEMENT, RAM STANDS FOR

A

RESOURCE ASSIGNMENT MATRIX

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A SIX-MONTH PROJECT YOU ARE ABOUT TO UNDERTAKE HAS A 10% CHANCE OF A RISK OCCURING IN ANY GIVEN MONTH. WHAT IS THE CHANCE THAT THE RISK WILL OCCUR DURING THE 5TH MONTH?

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

THE RFP, COST ESTIMATES, SOURCE SELECTION CRITERIA, AND “SOW” ARE ______

A

PROCUREMENT DOCUMENTS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

YOUR TEAM IS NOT GOING TO BE ABLE TO MEET A SOFTWARE INSTALLATION DEADLINE IN YOUR PROJECT. WHAT SHOULD YOU DO INTERNALLY ?

A

GENERATE A CHANGE REQUEST FOR CORRECTIVE ACTION

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

YOU WERE ALLOTTED $50,000 TO COMPLETE AN ACTIVITY FOR YOUR PROJECT. ACCORDING TO THE SCHEDULE, YOU SHOULD HAVE SPENT $25,000 FOR THE WORK PERFORMED TO THIS POINT, BUT YOU HAVE ONLY SPENT $22,250. WHAT IS THE PLANNED VALUE (PV)

A

$25,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

WHEN A CHANGE REQUEST IS APPROVED THROUGH THE INTEGRATED CHANGE CONTROL PROCESS, IT IS IMPLEMENTED THROUGH THE ____ PROCESS.

A

DIRECT AND MANGE PROJECT WORK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IN REVIEWING POSSIBLE FUNDING MECHANISMS FOR YOUR PROJECT, YOU MAY DECIDE TO USE AN ______ TO GENERATE SOME USEFUL INFORMATION FOR THE OVERALL COST MANAGEMENT PLAN

A

ALTERNATIVE ANALYSIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

THE PROJECT MANAGER’S AUTHORITY IS FORMALIZED WHEN THE ____ IS APPROVED

A

PROJECT CHARTER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A TOOL / TECHNIQUE THAT IS USEFUL DURING THE MONITORING / CONTROL PHASE OF THE PROJECT IS ______

A

INSPECTION

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

TO DETERMINE WHETHER THE PROJECT SCHEDULE IS STILL ON TRACK, THE PROJECT MANAGER MIGHT DECIDE TO COMPARE THE ACTUAL PROGRESS TO THE PREDICTED PROGRESS ALONG THE ____ ?

A

CRITICAL PATH

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

YOUR PROJECT IS FALLING BEHIND SCHEDULE AND YOU NEED TO BRING IT BACK INTO ALIGNMENT WITH YOUR SCHEDULE BASELINE. YOU DECIDE TO BRING IN THE EXTRA RESOURCES TO ACCOMPLISH THE WORK FASTER. THIS TECHNIQUE IS CALLED ____ .

A

CRASHING

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

WHILE PERFORMING COST CONTROL ACTIVITIES, THE LEAST HELPFUL INFORMATION WOULD BE

A

THE SCHEDULE BASELINE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

THE COST CONTROL PROCESS CAN INCLUDE THE FOLLOWING PROCESSES

A
  • COST MANAGEMENT PLAN
  • COST BASELINE
  • PERFORMANCE MEASUREMENT BASELINE
  • LESSONS LEARNED REGISTER
  • PROJECT FUNDING REQUIREMENTS
  • WORK PERFORMANCE DATA
  • EXISTING COST CONTROL ORGANIZATIONAL PROCESS ASSETS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

THE PROJECT MANAGER MONITORS USING THE CONTINGENCY AND MANAGEMENT RESERVES USING A ____ TO DETERMINE WHETHER THEY ARE SUFFICIENT TO COVER RISK RESPONSES.

A

RESERVE ANALYSIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

THE LOGISTICS DEPARTMENT IS NOT MAINTAINING AN ADEQUATE STOCK OF SUPPLIES LIKE PAPER AND TONER FOR YOUR PROJECT STAFF. WHAT SHOULD YOU DO?

A

TALK TO THE LOGISTICS DEPARTMENT MANAGER TO FIND THE PROBLEM AND A VIABLE SOLUTION

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

_____ DETERMINES WHETHER THE DELIVERABLE IS COMPLIANT WITH THE PROJECT GOALS AND OBJECTIVES.

A

QUALITY CONTROL

17
Q

FREQUENCY DATA, LIKE DEFECTS PER PROCESS, ARE BEST DISPLAYED GRAPHICALLY BY A ____

18
Q

AS THE NUMBER OF REJECTIONS HAS GONE DOWN EACH MONTH LISTED ON THE CHART, SO IT SHOWS THE DECREASED AMOUNT OVER TIME

19
Q

CRASHING A PROJECT MEANS TO

A

FIND PROCESSES THAT CAN BE IMPLEMENTED IN PARRALLEL INSTEAD OF CONSECUTIVELY AND CRASHING IT OR APPLY MORE RESOURCES TO THEM.

20
Q

THE PLANNED VALUE OR “PV” IS THE AMOUNT AUTHORIZED IN THE BUDGET FOR A SCHEDULED WORK

21
Q

THE PARETO PRINCIPLE STATES THAT 80% OF THE EFFECTS ARE FROM 20% OF THE CAUSES, FOR EXAMPLE, 80% OF PRODUCTS DEFECTS ARE FROM 20% OF THE PROCESSESS

22
Q

MANAGING PROJECT KNOWLEDGE INVOLVES LEVERAGING EXISTING KNOWLEDGE TO SUPPORT THE PROJECT OUTCOMES AND CREATING NEW KNOWLEDGE TO SUPPORT FUTURE PROJECTS

23
Q

THE PROJECT MANAGER NEEDS TO FIND OUT WHO SHOULD RECEIVE A REPORT ON THE METRICS OBTAINED FROM A QUALITY CONTROL REVIEW, SO SHOULD LOOK IN THE _____

A

QUALITY MANAGEMENT PLAN

24
Q

THE QUALITY MANAGEMENT PLAN ESTABLISHES WHAT?

A

THE QUALITY STANDARDS AND PROCEDURES FOR QUALITY DATA, INCLUDING THE FORMAT FOR RECORDING THE DATA ADN DETAILS ON SHAREING THE MEASUREMENTS AND RESULTS.

25
Q

____ MONITORING IS THE MOST EFFECTIVE AT DISCOVERING PROBLEMS QUICKLY