DP Activities Flashcards
1
Q
Directing a Project Process (5)
A
- Authorize Initiation
- Authorize the Project
- Authorize a Stage or Exception Plan
- Give Ad Hoc Direction
- Authorize Project Closure
2
Q
DP 1. Authorize Initiation (2)
PS
A
Project Brief
Stage Plan
3
Q
DP 2. Authorize the Project
LPB
A
Lessons Log
Project Initiation Documentation (PID)
Benefits Management Approach (BMA)
4
Q
DP 3. Authorize a Stage or Exception Plan (8)
SELFSEPB
A
Specialist Products End Stage Report Lessons Report Follow-on Action Recommendations Stage Plan for the next stage Exception Plan Updaed PID Updated BMA
5
Q
DP 4. Give Ad Hoc Direction (3)
HEI
A
Highlight Report
Exception Report
New Issue
6
Q
DP 5. Authorize Project Closure (5)
ELFBB
A
End Project Report Lessons Report Follow-on Action Recommendations Updated Business Case Updated BMA