Q
Controlling a Stage Process (3) (8)
A
A. Work Packages 1. Authorize a Work Package 2. Review Work Package Status 3. Receive Completed Work Packages B. Monitoring and Reporting 4. Review the Management Stage Status 5. Report Highlights C. Issues and Risks 6. Capture and Examine Issues and Risks 7. Escalate Issues and Risks 8. Take Corrective Action.
2
Q
CS 1. Authorize a Work Package (7)
WCQRITS
A
Work package Configuration item records Quality register Risk register Issue register Team plan Stage plan
3
Q
CS 2. Review Work Package Status (7)
CTSCRIW
A
Checkpoint Report Team plan Stage plan Configuration item records Risk Register Issue Register Work package
4
Q
CS 3. Receive Completed Work Packages (2)
CS
A
Configuration item records
Stage plan
5
Q
CS 4. Review the Management Stage Status (5)
RISLI
A
Risk Register Issue Register Stage plan Lessons Log Issue Report
6
Q
CS 5. Report Highlights (1)
H
A
Highlight Report
7
Q
CS 6. Capture and Examine Issues and Risks (4)
DIIR
A
Daily Log
Issue Report
Issue Register
Risk Register
8
Q
CS 7. Escalate Issues and Risks (4)
EIRI
A
Exception Report
Issue register
Risk register
Issue Report
9
Q
CS 8. Take Corrective Action (6)
IRISCD
A
Issue Register Risk Register Issue Report Stage Plan Configuration item records Daily Log