Closing a Project Process (5)
A
- Prepare Planned Closure
- Prepare Premature Closure
- Hand Over Products
- Evaluate the Project
- Recommend Project Closure
2
Q
- Prepare Planned Closure (2)
PP
A
Project Plan
Product Status Account
3
Q
- Prepare Premature Closure (4)
IPPA
A
Issue Register
Project Plan
Product Status Account
Additional Work Estimates
4
Q
- Hand Over Products (4)
FCBA
A
Follow-on Action Reccomendatiosn
Configuration item records
BMA
Acceptance Record
5
Q
- Evaluate the Project (2)
EL
A
End Project Report
Lessons Report
6
Q
- Recommend Project Closure (6)
IRQDLD
A